Title: Approve the award of Change Order #1 to Contract 26-132, South 40 Traffic Improvements, to Schroeder Asphalt Services, Inc. for an additional one year
Attachments: 1. South 40 - Contract Time Extension Letter Signed
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Change Order #1 to Contract 26-132, South 40 Traffic Improvements, to Schroeder Asphalt Services, Inc. for an additional one year
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: Jennifer Louden, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
City Council awarded Contract 26-132 to Schroeder Asphalt Services, Inc. with a completion date of December 18, 2026.  The purpose of this contract is to construct a new entrance on the east leg of the Illinois Route 59 and English Rows Avenue intersection. This includes a temporary roadway extending east from the intersection to the affordable housing for seniors and individuals with intellectual and developmental disabilities (IDD) project, and the addition of a southbound left-turn lane and northbound deceleration/right-turn lane on IL Route 59.

This project supports the development of the City-owned South 40 parcel, located at the southeast corner of IL Route 59 and 103rd Street and advances the City's initiative to provide affordable housing opportunities for seniors and adults with IDD. The developer of this housing project will be Gorman & Company, LLC (“Gorman”).

DISCUSSION:
This Change Order is requested due to delays in the completion of the overall South 40 development.

Because Gorman plans to utilize an affordable housing grant for the eastern parcel of the development, the site must undergo mandatory environmental clearances. The required environmental testing has delayed construction and, consequently, two soil stockpiles intended for that site remain in the project area of the temporary access road connecting the developments to IL Route 59. On-site construction cannot proceed until these stockpiles are removed, which is not anticipated to occur until July 2027.

The initial contract completion date was December 18, 2026. Instead of completing a portion of the IL Route 59 improvements in 2026, all contra...