File #: 21-1404    Version: 1
Type: Procurement Award Status: Passed
File created: 10/27/2021 In control: City Council
On agenda: 12/7/2021 Final action: 12/7/2021
Title: Approve the award of Bid 21-223, Springbrook Water Reclamation Center Influent Flow Meter Replacement, to Dahme Mechanical Industries, Inc. for an amount not to exceed $158,888.88 and a 5% contingency
Attachments: 1. WW041
Related files: 22-0511, 22-1403
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Bid 21-223, Springbrook Water Reclamation Center Influent Flow Meter Replacement, to Dahme Mechanical Industries, Inc. for an amount not to exceed $158,888.88 and a 5% contingency
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Darrell Blenniss, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
There are currently three existing meters to measure flow from the influent pump station to the north and south plants at Springbrook. Measurement of flow is required as part of the City's National Pollutant Discharge Elimination System (NPDES) permit compliance. The existing flow meters are approximately 22 years old and have reached the end of their useful life.

In October 2021, the Water Utilities issued Bid 21-223, Springbrook Water Reclamation Center Flow Meter Replacement. The contractor will replace the three existing influent flow meters at the Springbrook Water Reclamation Center. The contractor will furnish all materials, equipment, tools and labor to properly complete work. An additive alternate was also included to rotate the existing plug valves in the flow meter vaults so they can be modified for operation with a key.

DISCUSSION:

Advertisement Date: 10/27/2021 Notices Sent: 70
Bid Opening Date: 11/16/2021 Planholders: 27
Proposals Received: 2

Vendors Name
Proposed Base Bid Cost
Alternate Bid Costs
Engineers Estimate
$130,000
$40,000
Dahme Mechanical Industries
$158,888.88
$58,888.88
AMS Mechanical Systems Inc.
$163,504.00
$38,000.00

The current bidding climate, as well as continuing supply chain and labor availability issues related to COVID-19, makes estimating project costs difficult resulting in the engineer's estimate being lower than the bids received. Staff evaluated base bids and alternate bids and elected to proceed with the base bid only at this time.

The completion date of this project is June 1, 2022. Staff worked with the contracto...

Click here for full text