File #: 24-0969    Version: 1
Type: Report Status: Agenda Ready
File created: 8/15/2024 In control: Riverwalk Commission
On agenda: 9/11/2024 Final action:
Title: Receive the six-month Naperville Riverwalk financial report
Attachments: 1. Riverwalk Financial Report through June 30, 2024
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

RIVERWALK COMMISSION AGENDA ITEM

 

ACTION REQUESTED:
title

Receive the six-month Naperville Riverwalk financial report

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     William J Novack, P.E., Director of Transportation, Engineering and Development/City Engineer

 

BOARD/COMMISSION REVIEW:
NA

 

BACKGROUND:

The City of Naperville has an annual budget.  The City’s budget year is the same as the calendar year.  The Riverwalk Commission’s budget includes some smaller operating expenses along with our much larger capital improvement expenses.

 

Financial reports are provided to the Riverwalk Commission after the six-month and end of year close, usually in September and March.

 

DISCUSSION:

Attached is the six-month financial report through June 30, 2024.  The first page shows both the capital and the operating budgets while the second page shows the individual capital projects. 

 

Overall, we have spent only 4.2% of our budget halfway through the fiscal year.  This low amount is being driven by the fact that we have spent only 2.8% of our capital budget, which is over eighty percent of our budget.  The reasons for the low capital spending amounts are the rejection of the bids for the Eagle Street Gateway and the construction delays on the fountain repairs.  The capital spending will rise a little during the second half of the year, but not significantly due to the much higher cost of the Eagle Street Gateway project.