File #: 23-0024    Version: 1
Type: Cash Disbursements Status: Agenda Ready
File created: 1/5/2023 In control: City Council
On agenda: 1/17/2023 Final action:
Title: Approve the payment of $162,750 to DuPage County for off-site wetland mitigation for the North Aurora Road Underpass project
Attachments: 1. Invoice from DuPage County for wetland banking fee
Related files: 23-1521
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the payment of $162,750 to DuPage County for off-site wetland mitigation for the North Aurora Road Underpass project
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: William J. Novack, Director/City Engineer

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The City of Naperville and our project partners at Naperville Township and the City of Aurora have been finishing up the design and permitting for the improvements to the North Aurora Road underpass at the Canadian National railroad located approximately one mile west of Illinois Route 59. There are existing wetlands within the project limits that will be impacted and cannot be mitigated as part of the project. The only mitigation option available is to purchase wetland credits from a wetland bank.

DuPage County and the US Army Corps of Engineers are the regulatory agencies responsible for wetland permitting. Both agencies have agreed that wetland banking is appropriate for this project. A wetland mitigation banking fee must be paid to both agencies for this project because there are no available wetland banks in the West Branch of the DuPage River watershed.

DISCUSSION:
The project impacts 0.62 acres of wetland. Due to the quality of the wetland it must be mitigated at a 1.5 to 1 ratio. At $175,000 per acre the fee to DuPage County is $162,750. Attached is the invoice from the County for this mitigation.

The Army Corps is still establishing their next available wetland bank (located in the Des Plaines River watershed), so the final costs to the Army Corps is not known yet. It is believed it will be of similar value to the DuPage County cost. Once that amount is known and they issue us an invoice we will return for approval of that payment.

The Intergovernmental Agreement with our project partners stipulates that the three partners will equally share in the cost of the wetland mitigation. Since the City of Napervil...