Legislation Details

File #: 26-1271    Version: 1
Type: Procurement Change Order Status: Agenda Ready
File created: 10/26/2026 In control: City Council
On agenda: 12/1/2026 Final action:
Title: Approve the award of Change Order #1 to Work Order 26-053-TED-26-02, South 40 Traffic Improvements, to Christopher B Burke Engineering LTD. for an additional one year
Attachments: 1. South 40 - Contract Time Extension Letter Signed
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Change Order #1 to Work Order 26-053-TED-26-02, South 40 Traffic Improvements, to Christopher B Burke Engineering LTD. for an additional one year
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: Jennifer Louden, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
City Council awarded Work Order 26-053-TED-26-02 to Christopher B Burke Engineering LTD with a completion date of December 18, 2026.  The purpose of this work order is to provide Phase III engineering services for Contract 26-132 to construct a new entrance on the east leg of the IL Route 59 and English Rows Avenue intersection. This includes a temporary roadway extending east from the intersection to the affordable housing for seniors and individuals with intellectual and developmental disabilities (IDD) project, and the addition of a southbound left-turn lane and northbound deceleration/right-turn lane on IL Route 59.

This project supports the development of the City-owned South 40 parcel, located at the southeast corner of IL Route 59 and 103rd Street. The development advances the City's initiative to provide affordable housing opportunities for seniors and adults with IDD. The developer of this housing project will be Gorman & Company, LLC (“Gorman”).

DISCUSSION:
This Change Order is requested due to delays in the completion of the overall South 40 development.

Because Gorman plans to utilize an affordable housing grant for the eastern parcel of the development, the site must undergo mandatory environmental clearances. The required environmental testing has delayed construction on the east parcel, and consequently, two soil stockpiles intended for that site remain within the project area of the temporary access road connecting the developments to IL Route 59. On-site construction cannot proceed until these stockpiles are removed, which is not anticipated to occur until July 2027.

The initial contra...

Click here for full text