File #: 22-0671    Version: 1
Type: Procurement Award Status: Passed
File created: 5/23/2022 In control: City Council
On agenda: 6/7/2022 Final action: 6/7/2022
Title: Approve the award of Change Order #2 to Contract 20-322, Water Utilities MDMS Software and Support (AMI Project), to Harris Computer Systems for an additional 185 days (Item 2 of 2)
Attachments: 1. WU040
Related files: 20-983, 20-986
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Change Order #2 to Contract 20-322, Water Utilities MDMS Software and Support (AMI Project), to Harris Computer Systems for an additional 185 days (Item 2 of 2)
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Darrell Blenniss, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
In 2010, the Electric Utility purchased the Harris meter data management system (MDMS) to house all meter and customer data to facilitate billing. The system provides a single repository for information and allows Electric to analyze consumption data to assist in rate development, as well as to make better decisions for transformer sizing. Additionally, data in the MDMS is used for the Empower customer portal, which provides customers an easy way to view consumption in daily, weekly, monthly, and yearly formats.

On September 1, 2020, Council approved a sole source to allow Harris to expand the existing meter data management system to include Water Utility data. Council approved Change Order #1 on December 21, 2021, adding 180 days to the contract.

DISCUSSION:
The MDMS for the Water Utility will provide similar benefits including long-term meter data storage and data analytics. Additionally, the Empower customer portal will leverage the integrations to allow customers to view water consumption, make informed decisions, and enable customers to partner with the Water Utility to operate more efficiently.

A change order is requested to extend the contract by 185 days allowing the contractor to complete the software integrations, testing, and final invoicing as specified in the contract. This will align the term with the City's related contract with Core & Main. Upon approval, the revised completion date will be December 31, 2022. Staff will continue to work with the vendor to expedite completion of the project and no additional funds are required to complete the outstanding work.

FISCAL IMPACT:
CIP: WU040

Installa...

Click here for full text