File #: 24-1284    Version: 1
Type: Procurement Award Status: Passed
File created: 10/31/2024 In control: City Council
On agenda: 11/19/2024 Final action: 11/19/2024
Title: Approve the award of Bid 24-161, South Plant Return Activated Sludge and Grit Improvements, to Vissering Construction Company for an amount not to exceed $14,077,000 plus a 3% contingency
Related files: 25-0488
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Bid 24-161, South Plant Return Activated Sludge and Grit Improvements, to Vissering Construction Company for an amount not to exceed $14,077,000 plus a 3% contingency
body

DEPARTMENT: Water Utilities

SUBMITTED BY: Darrell Blenniss, Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The City of Naperville completed a Facilities Plan for Springbrook Water Reclamation Center (SWRC) in 2021. The Facilities Plan supports the City's Utilities priority of protecting the health and welfare of our customers and meeting regulatory requirements.

Specifically, the Facilities Plan identified a long-term strategy to plan improvements at SWRC to comply with the City's National Pollutant Discharge Elimination System (NPDES) permit. It also anticipates future regulations, particularly related to nutrient removal and the South Plant return activated sludge (RAS) and grit improvements were identified as a key project in the plan.

In September 2024, the Water Utilities issued Bid #24-161, South Plant RAS and Grit Improvements. The construction work includes replacing the existing aerated grit system with an improved grit removal system and increasing RAS pumping capacity to accommodate future flows, nutrient removal and Side-Stream Enhanced Biological Phosphorus Removal (S2EBPR).

DISCUSSION:

Advertisement Date:
9/10/2024
Notices Sent:
271
Opening Date:
10/23/2024
Plan holders:
40


Proposals Received:|1010|
Bids were received from the following vendors:

Vendor Name
Proposed Cost
Engineer's Estimate
$12,213,164
Vissering Construction Company
$14,077,000
Joseph J. Henderson & Son, Inc.
$14,176,500
IHC Construction Companies, LLC
$15,146,000
Williams Brothers Construction Inc.
$15,760,000
John Burns Construction Company
$16,996,000

Vissering Construction Company submitted the lowest bid for the project, $14,077,000. Staff believe the low bid is reasonable for the specified work. Vissering Constructi...