File #: 17-718    Version: 1
Type: Ordinance Status: Passed
File created: 9/11/2017 In control: City Council
On agenda: 9/19/2017 Final action: 9/19/2017
Title: Pass an Ordinance authorizing a delegated sale of General Obligation (G.O.) Bonds for an amount not to exceed $8,250,000
Attachments: 1. Naperville 2017 - Authorizing Ordinance
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Pass an Ordinance authorizing a delegated sale of General Obligation (G.O.) Bonds for an amount not to exceed $8,250,000
body

DEPARTMENT: Finance Department

SUBMITTED BY: Rachel Mayer, Finance Director

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
The City Council, at the Budget Workshops held on October 24, 2016, November 14, 2016 and November 28, 2016, reviewed the proposed Calendar Year 2017-2021 Capital Improvements Program (CIP). The final proposal included $57.4 million in Capital Improvements with an $8 million projected required borrowing. At the December 5, 2016 City Council meeting, the Council approved this budget.

On January 17, 2017, the City Council adopted a resolution of Official Intent for Reimbursement of Capital Projects. This allowed all projects approved through the CY2017 budget to be included in any future bond sale. However, the resolution did not provide the authorization to borrow, it only reserved the ability to fund current projects with a future G.O. bond sale.

While Staff had originally projected an issuance in June 2017, staff was able to postpone the borrowing based on cashflow needs and thus reduced incurring additional interest costs.

DISCUSSION:
Staff is proposing to issue $8.25 million in general obligation bond for new projects at a projected rate of 3.50%. As part of the CY2017-2021 Capital Improvement Program (CIP), City Council conceptually approved borrowing for a portion of the projects. The City proposes to issue Series 2017 G.O. Bonds of which the proceeds of this sale will fund the current capital projects including the following:
Project List
Estimated Costs
E-Government Initiatives
$1,560,000
Building Maintenance & Upgrade Projects
$1,915,000
Stormwater Management Programs
$305,000
Traffic Improvement Programs
$4,470,000
TOTAL
$8,250,000

The 2017 issuance for G.O. bonds will have their first payment in 2018 and their projected final payment will occur in 20...