File #: 21-0857    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 6/23/2021 In control: City Council
On agenda: 8/17/2021 Final action: 8/17/2021
Title: Approve the award of Bid 21-232, 2021 New Sidewalk Improvements Program, to Triggi Construction, for an amount not to exceed $239,558.00, plus a 5% contingency
Attachments: 1. CIP PAGE
Related files: 22-0006
CITY COUNCIL AUTHORITY PROCUREMENT AWARD

ACTION REQUESTED:
title
Approve the award of Bid 21-232, 2021 New Sidewalk Improvements Program, to Triggi Construction, for an amount not to exceed $239,558.00, plus a 5% contingency
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: William J. Novack, Director

BACKGROUND:
The purpose of the Comprehensive Sidewalk Plan ("Plan") is to improve walkability throughout the City.

In 2019, the selection process for the New Sidewalk Program was revised to help better prioritize the remaining sidewalk gaps in the City as identified in the Plan. Using this process, a two-year program identifying the next set of sidewalk gaps to be filled was created and then approved by TAB and City Council.

For the first year of the program, in June 2021, the Transportation, Engineering and Development (TED) Business Group issued Bid 21-232, 2021 New Sidewalk Improvements Program.

The 2021 program will install the higher-scoring sidewalk gaps (list shown below). The Porter Avenue location, originally proposed for the first year of the program, was postponed to the second year.

* Eagle Street, east side between 13th and 14th Avenue
* Sleight Street, east side from Ogden Avenue north to dead end
* Sleight Street, west side between Porter and Highland Avenue
* Washington Street, east side between Pioneer Park and Gartner Road
* Webster Street, west side between Ogden and 10th Avenue
* Wehrl Drive, east side between View Court and Hillside Road
* Willow Road, west side between Maple Lane and Hillside Road

DISCUSSION:

Advertisement Date:
06/25/21
Notices Sent:
106
Opening Date:
07/21/21
Planholders:
18


Proposals Received:
6

Bids were received from the following vendors:

Vendor Name
Proposed Cost
Engineer's Estimate
$297,283.00
TRIGGI CONSTRUCTION
$239,558.00
A LAMP CONCRETE CONTRACTORS
$253,859.00
SCHROEDER & SCHROEDER INC
$280,175.00
ALLIANCE CONTRACTORS INC
$282,768.00
COPENHAVER CONSTRUCTION INC
$288...

Click here for full text