CITY COUNCIL AGENDA ITEM
ACTION REQUESTED:
title
Approve the award of Change Order #2 to Option Year #2 of Contract 22-100, Transmission & Distribution Engineering Services, to Primera Engineers for an additional six months
body
DEPARTMENT: Electric Utility
SUBMITTED BY: Raheel Arshed, Deputy Director
BOARD/COMMISSION REVIEW:
N/A
BACKGROUND:
The City Council awarded Change Order #1 to Option Year #2 of Contract 22-100, Transmission & Distribution Engineering Services, to Primera Engineers for an additional 271 days.
The purpose of this contract is to contract with an experienced and qualified firm to offer supplemental engineering services for the Electric Utility (“Utility”) as needed for capital improvement, maintenance, and new business projects.
Primera has completed 11 projects for the Utility, however, three separate 138kV breaker replacement designs for the City’s Pebblewood, Meadows, and Springbrook substations have been delayed. The breakers being replaced at these stations are beyond expected life and are becoming difficult to maintain due to lack of manufacturer support.
DISCUSSION:
The requested Change Order will extend the project completion date by six months, establishing a new completion date of June 30, 2027. The extension is necessary due to delays in receiving the required soil boring reports, which impacted the project schedule and Primera’s ability to proceed with the planned work. Although the Utility received the soil boring reports in March 2026, the revised drawings were not returned to the Utility until October 2026. The additional time will allow the Utility to review and finalize the drawings, complete the remaining project work, and provide Primera with sufficient time to prepare and submit the final as-built drawings.
Three 138kV circuit breaker replacement projects were impacted by these delays and are currently in different stages of completion. A key design component for the breaker replacements is validating that the e...