File #: 24-0973    Version: 1
Type: Change Order & Work Order Status: Agenda Ready
File created: 8/16/2024 In control: City Council
On agenda: 9/3/2024 Final action:
Title: Approve the award of Change Order #1 to Contract 24-007, Parking Lot and Multi-Use Path Maintenance, to Denler, Inc. for an amount not to exceed $79,445.83 and a total award of $1,221,816.26
Attachments: 1. PorterParkingLot_ExhibitAndEstimate_City_Denler_2024
CITY COUNCIL AGENDA ITEM

ACTION REQUESTED:
title
Approve the award of Change Order #1 to Contract 24-007, Parking Lot and Multi-Use Path Maintenance, to Denler, Inc. for an amount not to exceed $79,445.83 and a total award of $1,221,816.26
body

DEPARTMENT: Transportation, Engineering and Development

SUBMITTED BY: William J. Novack, P.E., Director of Transportation, Engineering and Development/City Engineer

BOARD/COMMISSION REVIEW:
N/A

BACKGROUND:
In May 2024, the Transportation, Engineering and Development Business Group (TED) issued Bid 24-007 seeking contractors to perform maintenance and repairs on city-maintained parking lots and multi-use paths. This was a joint project involving TED, the Water Utility and the Electric Utility. Maintenance required by these departments are combined into one project that is managed by TED.

City Council awarded Bid 24-007 to Denler, Inc., on June 4, 2024, with a completion date of October 18, 2024. The maintenance work under this contract ranges from low-impact maintenance such as crack sealing and parking stall painting, to high-impact maintenance like seal coating, patching, and resurfacing.

DISCUSSION:
This change order is requested to add the unanticipated Naper Settlement Porter Avenue Parking Lot resurfacing and restriping project to Bid 24-007, so it can be completed in 2024 using current Buildings & Grounds budget funds.

The Porter Avenue Parking Lot requires high-impact maintenance based on the life of the pavement. To address the existing surface deficiencies, including substantial cracking and several potholes, resurfacing is recommended for this parking lot. In addition, a small section of curb and sidewalk will be rebuilt at the northeast corner of the parking lot to improve accessibility. The Buildings & Grounds Department recommends this work be completed in 2024 before the busy school tour season and winter weather.

Denler, Inc. has confirmed that this work can be added to the existing contract with...

Click here for full text