File #: 19-206    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 2/28/2019 In control: City Council
On agenda: 3/19/2019 Final action: 3/19/2019
Title: Approve the award of Bid 19-003, 2019 Crackfilling Program, to Denler, Inc. for an amount not to exceed $331,710, plus a 5% contingency
Attachments: 1. CIP Page

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 19-003, 2019 Crackfilling Program, to Denler, Inc. for an amount not to exceed $331,710, plus a 5% contingency

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     William Novack, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The Transportation, Engineering and Development Business Group issued Bid 19-003 seeking vendors to perform fiberized crackfilling on various City streets. Crackfilling consists of cleaning and sealing of any cracks, voids or joints 2 inches in width or less with asphalt cement reinforced by polypropylene fibers.  It is a cost effective preventative maintenance technique and when performed routinely, can keep water and debris from getting into pavement. 

 

DISCUSSION:

 

Advertisement Date:

2/13/19

Notices Sent:

 41

Opening Date:

2/28/19

Planholders:

   7

 

 

Proposals Received:

   2

 

Bids were received from the following vendors:

 

Vendor

Proposed Cost

Denler, Inc.

$331,710

Engineer’s Estimate

$348,700

SKC Construction

$350,510

 

FISCAL IMPACT:

CIP # MP009 - Street Maintenance Improvement Program (MIP)

 

The MIP is expensed to the following accounts listed below. A total of $11 million has been budgeted for the MIP in 2019. The requested amount is within budget.

 

Account Number

Fund Description

Total Budget Amount

30282200-551502

Capital Projects

$8,331,416.37

30282400-551502

Road and Bridge

$2,165,000

30282500-551502

Motor Fuel Tax

$3,850,000

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.