File #: 22-0511    Version: 1
Type: Procurement Award Status: Agenda Ready
File created: 4/18/2022 In control: City Council
On agenda: 5/3/2022 Final action:
Title: Approve the award of Change Order #1 to Contract 21-223, Springbrook Water Reclamation Center Influent Flow Meter Replacement, to Dahme Mechanical Industries, Inc. for an additional 184 days
Attachments: 1. WW041
Related files: 21-1404, 22-1403

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #1 to Contract 21-223, Springbrook Water Reclamation Center Influent Flow Meter Replacement, to Dahme Mechanical Industries, Inc. for an additional 184 days

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

At the December 7, 2021, meeting, City Council approved the award of Bid 21-233, Springbrook Water Reclamation Center Influent Flow Meter Replacement, to Dahme Mechanical Industries for an amount not to exceed $158,888.88 and a 5% contingency. The work includes the replacement of three existing influent flow meters at the Springbrook Water Reclamation Center. The original contract completion date is June 1, 2022. 

 

DISCUSSION:

Persistent global supply chains issues have resulted in delays in obtaining the flow meters. A change order is requested to extend the contract completion date by 184 days to allow the contractor to complete the work as specified. If approved, the revised contract completion date will be December 1, 2022.

 

Staff will work with the vendor to expedite the completion of the project once the equipment is received.

 

FISCAL IMPACT:

CIP: WW041

 

The requested change order adds 184 days to the contract but does not change the cost of the project. There is no direct fiscal impact resulting from this change.