Skip to main content
File #: 25-1299    Version: 1
Type: Report Status: Agenda Ready
File created: 9/26/2025 In control: Riverwalk Planning, Design and Construction Committee
On agenda: 9/30/2025 Final action:
Title: Receive the update on various ongoing Riverwalk projects
Attachments: 1. Riverwalk Project Photos
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

RIVERWALK PLANNING, DESIGN AND CONSTRUCTION COMMITTEE AGENDA ITEM

 

ACTION REQUESTED:
title

Receive the update on various ongoing Riverwalk projects

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     Andrew Hynes, P.E., Deputy Director of Transportation, Engineering and Development/City Engineer 

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

Three projects on or adjacent to the Riverwalk are currently in progress:

                     Eagle Street Gateway

                     Fredenhagen Park Fountain Repairs

                     Fredenhagen Park Miscellaneous Repairs

 

A status update for each project is provided below.

 

 

DISCUSSION:

Eagle Street Gateway

Construction continues the Eagle Street Gateway project.  See attached photo. Various retaining walls, staircase components, and landscaping have been installed over the past few weeks.  Completion is expected in October.

 

Fredenhagen Park Fountain Repairs

The contractor has installed the conduit and Park Distrct staff have restored the brick pavers.  See attached photo. The next step will be the application of the new waterproof liner pending appropriate weather conditions.  The project is expected to be completed in October with activation of the fountain to follow.

 

Fredenhagen Park Miscellaneous Repairs

The cleaning and staining work on various features within Fredenhagen Park is complete.  See attached photos.