File #: 24-0054    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 1/10/2024 In control: City Council
On agenda: 2/6/2024 Final action: 2/6/2024
Title: Approve the award of Bid 24-014, Small Diameter Sanitary Sewer Main Lining Program - 2024, to Hoerr Construction, for an amount not to exceed $619,182 and a 3% contingency

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 24-014, Small Diameter Sanitary Sewer Main Lining Program - 2024, to Hoerr Construction, for an amount not to exceed $619,182 and a 3% contingency

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The Water Utilities 2024 Capital Improvement Plan (CIP) includes rehabilitation of approximately 50 manholes, 13,985 linear feet of sanitary main/trunk sewers, and 235 sewer service laterals. The primary focus of these projects is to reduce leakage of groundwater and surface water into the system. The sanitary sewer main lining program is part of the Water Utilities' Illinois Environmental Protection Agency (IEPA) required capacity, management, operation, and maintenance (CMOM) plan and ten-year infiltration and inflow reduction program. These requirements are under Naperville's National Pollutant Discharge Elimination System permit IL0034061.

 

Sanitary sewer lining is a major component of the City's strategy to reduce system leaks associated with stormwater infiltration through pipe cracks and fissures, which reduces sanitary system capacity during wet weather events. Lining the sewer provides seamless, leak-free pipes and maintains structural integrity for approximately 50 years. Reducing leaks and preserving system capacity also help reduce the number and severity of sanitary sewer backups.

 

DISCUSSION:

In December 2023, the Water Utilities issued Bid 24-014, 2024 Small Diameter Sanitary Sewer Main Lining. This bid will rehabilitate 13,985 linear feet of eight-inch through fifteen-inch diameter sanitary sewer pipeline located in Naperville Center of Commerce & Industrial Park located North Aurora Road and Diehl Road. The contractor will use no-dig lining technology to reduce costs and disruption to the community.

 

To secure the lowest possible pricing, the bid specified two competing lining technologies: glass-reinforced plastic (GRP) and cured-in-place thermosetting resin pipe (CIPP).

 

Advertisement Date: 12/15/2023

 

Notices Sent: 614

 

Opening Date: 1/9/2024

 

Planholders: 20

 

 

 

Proposals Received: 5

 

 

 

Vendor

Bid Amount

Hoerr Construction

$619,182.00

Engineer Estimate

$635,500.00

Performance Pipeline

$664,902.00

Visu-Sewer Clean and Seal

$703,733.65

National Power Rodding Corporation

$706,772.75

Insituform Technologies USA, LLC.

$742,679.77

 

Hoerr Construction is the lowest responsive and responsible bidder. The Water Utility has worked with this contractor in the past and the work was satisfactory. The completion date of this project is December 31, 2024.

 

FISCAL IMPACT:

CIP#: WW058

Rehabilitation of the small diameter sanitary sewer main in the Naperville center of commerce and industrial park, is budgeted in the account number listed below as part of the Water Capital Program. A total of $679,800 is approved for this project as part of the 2024 CIP. The requested award including the contingency amounts are within the budget.

 

Account

Fund Description

Total Account Budget

41252000-551502

Water Capital Fund

$40,264,902

 

Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.