File #: 25-1616    Version: 1
Type: Procurement Change Order Status: Agenda Ready
File created: 12/2/2025 In control: City Council
On agenda: 12/16/2025 Final action:
Title: Approve the award of Change Order #2 to Contract 25-041, Fire Station Renovations - Stations #1 and #3, to Lite Construction for an amount not to exceed $40,082 and a total award of $833,272
Related files: 25-0368, 25-1065
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #2 to Contract 25-041, Fire Station Renovations - Stations #1 and #3, to Lite Construction for an amount not to exceed $40,082 and a total award of $833,272

body

 

DEPARTMENT:                     Fire Department

 

SUBMITTED BY:                     Mark Puknaitis, Fire Chief

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The City Council awarded Contract 25-041, Fire Station Renovations - Stations #1 and #3, to Lite Construction on April 2, 2025, with a completion date of December 15, 2025. Change Order #1 was approved on August 19, 2025. The purpose of this contract is to renovate Fire Stations #1 and #3 from common sleeping and bathing areas into individual bunks and single-use bathrooms/showers.

 

DISCUSSION:

This Change Order is requested to pay for temporary restroom and shower trailers used by firefighters at each station during the renovations and additional cove base molding required for floor installation. Temporary restroom and shower facilities were not included in the original bid scope; however, procuring these services through the general contractor proved to be the most efficient and cost-effective means. This Change Order serves as the final payment for this project.

 

This contract was approved with contingency in the amount of 3% of the original contract value and 29 days.  Staff requests the use of contingency funds of $22,677, plus an additional $17,405, for a total change order of $40,082.  A summary of the award and contingency information is provided in the tables below.

 

Contingency

Authorized Contingency

Dollars

Original Amount

$22,677

(-) Previously Authorized

$0

Subtotal

$22,677

(-) This Change

$22,677

Balance Left

$0

 

Contract Award

Original Contract Value

$755,900

Prior Cumulative Approved Change Orders

$37,290

Subtotal

$793,190

(+/-) This Change Order

$40,082

Total Contract Value

$833,272

 

 

FISCAL IMPACT:

CIP #: MB226 - Fire Station Living Quarters Renovation

 

Renovations to the fire station living quarters are expensed to the Building Improvements account listed below. This work is being done in conjunction with MB226, Fire Station Living Quarters Renovation, which has a total budget of $1,500,000 in 2025. This Change Order utilizes previously approved contingency funds, in part, and the additional funds can be accommodated within the budget.

 

Account Number

Fund Description

Total Budget Amount

22252200-551500

Capital Projects Fund

$2,050,000

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.