Title: Approve the award of Bid 25-289, 2025 New Sidewalk Improvements Program, to Triggi Construction, Inc. for an amount not to exceed $309,343 plus a 5% contingency

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 25-289, 2025 New Sidewalk Improvements Program, to Triggi Construction, Inc. for an amount not to exceed $309,343 plus a 5% contingency

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     Jennifer Louden, Director of TED

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

In 2022 and 2023, the Transportation Advisory Board (TAB) and City Council approved a three-year New Sidewalk Program, whose purpose is to improve walkability throughout the City. The first year of this program was constructed in 2023. This award is for year three.

 

In September 2025, the Transportation, Engineering and Development Business Group (TED) issued Bid 25-289, 2025 New Sidewalk Improvements Program, to conduct work that consists of sidewalks, driveways, curb and gutter, tree pruning, tree relocation, excavation, sodding, erosion control, mobilization, brick pavers, modular block retaining walls, traffic control, and other incidental and miscellaneous items of work per the plans, standard specifications, and special provisions. This project includes the following locations:

                     Villa Ave and Wright St (northeast corner)

                     10th Ave (north side), Webster St to Main St

                     11th Ave (north side), Main St to Washington St

                     12th Ave (north side), Main St to Washington St

                     14th Ave (south side), Eagle St to Main St

                     Main St (west side), 11th Ave to 14th Ave

                     Webster St (east side), 10th Ave to 11th Ave

                     Webster St (east side), 12th Ave to 14th Ave

 

DISCUSSION:

 

Advertisement Date:

09/18/2025

Notices Sent:

207

Opening Date:

10/09/2025

Plan holders:

24

 

 

Proposals Received:

9

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Cost

Triggi Construction, Inc.

$309,343.00

Everlast Blacktop

$341,673.66

Miller Pipeline, LLC

$362,852.70

Schroeder & Schroeder, Inc.

$397,700.00

Engineer’s Estimate

$408,770.78

Alliance Contractors, Inc.

$428,606.23

G&M Cement Construction, Inc.

$434,227.53

Copenhaver Construction

$454,917.53

Tiles in Style, LLC

$556,604.00

Martam Construction, Inc.

$557,788.00

 

Triggi Construction, Inc. has successfully performed this program in years past. Staff recommends award of the contract to Triggi Construction, Inc. as the lowest responsive and responsible bidder for the procurement of construction services, as defined by Section 1-9B-7 of the Procurement Code (RBO-qualified).

 

The completion date of this project is May 30, 2026.

 

FISCAL IMPACT:

CIP #: CS006

 

The New Sidewalk Program is expensed to the Infrastructure and Architect and Engineering Services accounts listed below. TED included $445,000 in the 2025 budget for work related to CS006. The award requested is within the amount budgeted for this expense.

 

Account Number

Fund Description

Total Budget Amount

30282200-551502

Capital Projects Fund

$12,350,780

30282200-531301

Capital Projects Fund

$3,642,102

 

*Per Council directive, contingency on construction projects is set at 3% on projects