File #: 24-1246    Version: 1
Type: Procurement Award Status: Passed
File created: 10/25/2024 In control: City Council
On agenda: 12/3/2024 Final action: 12/3/2024
Title: Approve the award of Bid 24-211, 2025 Lead Water Service Replacement Program, to Trine Construction Corporation for an amount not to exceed $800,000 plus a 3% contingency
Attachments: 1. 2025LSLRProjectArea
Related files: 25-0488

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 24-211, 2025 Lead Water Service Replacement Program, to Trine Construction Corporation for an amount not to exceed $800,000 plus a 3% contingency

body

 

DEPARTMENT:                      Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

In support of the City’s priority of providing utility services that are reliable and safe, in September 2024, the Water Utilities issued Bid 24-211, 2025 Lead Water Service Replacement Program.  The Lead Water Service Replacement Program is a City initiative to replace all known lead water service lines with copper water service lines starting in 2024. This work will continue as long as necessary to remove all lead water service lines from the system.  Work includes the replacement of the entire length of the water service line, from the water main to inside the residence, at no cost to the property owner. 

 

The work within this contract will be completed in 2025 with subsequent years being bid separately.  With approximately 263 known lead water services remaining in the City, completion of the full program is anticipated to take several years.  The 2025 project includes the full replacement of approximately 68 lead water services in an area generally located between Chicago Avenue and 4th Avenue and Ellsworth Street and Columbia Street.

 

DISCUSSION:

 

Advertisement Date:

9/162024

Notices Sent:

390

Opening Date:

10/18/2024

Planholders:

40

 

 

Proposals Received:

10

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Cost

Trine Construction Corporation

$800,000

Miller Pipeline LLC

$1,060,300

Engineer’s Estimate

$1,152,450

Brandt Excavating

$1,272,782

IHC Construction Companies, LLC

$1,436,472

Benchmark Construction

$1,488,103

Five Star Energy Services, LLC

$1,535,910

Performance Construction & Engineering

$1,831,845

Bluewater Construction, LLC

$1,890,390

Everlast Blacktop

$2,096,517

Sheridan Plumbing & Sewer, Inc

$2,640,555

 

Trine Construction Corporation submitted the low bid for the project at $800,000.  The low bid is 20% lower than the 2025 budget amount of $1,000,000.

 

Staff believes the low bid submitted is reasonable for performing the work as specified. Upon checking the references provided, staff finds them to be a capable contractor.

 

The estimated completion date for this project is October 31, 2025.

 

FISCAL IMPACT:
CIP #: WU037 - Lead Service Replacements

 

This project is expensed to the account number listed below. The proposed 2025 budget includes $1,000,000 for this project. The requested award including the contingency is $176,000 under budget.

 

Account Number

Fund Description

Proposed Budget

41251500-551502

Water Utility Fund

$68,654,488

 

 

 

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.