Legislation Details

File #: 26-1363    Version: 1
Type: Procurement Change Order Status: Agenda Ready
File created: 11/13/2026 In control: City Council
On agenda: 12/1/2026 Final action:
Title: Approve the award of Change Order #2 to Contract 21-355, Tollway Substation Reliability Upgrade, to Sargent & Lundy, LLC for an additional 12 months
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #2 to Contract 21-355, Tollway Substation Reliability Upgrade, to Sargent & Lundy, LLC for an additional 12 months

body

 

DEPARTMENT:                     Electric Utility

 

SUBMITTED BY:                     Raheel Arshed, Deputy Director

 

BOARD/COMMISSION REVIEW:

BACKGROUND:

The Electric Utility (Utility) Tollway Substation has experienced several 34.5kV bus flashovers in recent years. These flashovers cause extended outages to critical industrial and commercial customers along the I-88 corridor.  The primary cause of these failures is due to salt contamination from the tollway. Relocating the 34.5kV bus indoors will eliminate the primary cause of failures.

 

In February 2022, the City Council awarded Contract 21-355, Tollway Substation Reliability Upgrade, to Sargent & Lundy with a completion date of December 31, 2025. The purpose of this contract is for the development of a complete engineering design, construction support, and as-built incorporation for the Tollway Substation to address the reliability concerns.

 

This Change Order is requested to support a scope change from the original award.  The construction to the Tollway Substation Building has started and the completion date of the building has been pushed back to May 2027.

 

DISCUSSION:

The original scope awarded to Sargent & Lundy included developing specifications for a prefabricated aluminum control building to house indoor 34kV switchgear and integrating the building with the existing and new system protection schemes. After reviewing vendor specifications and preliminary pricing, the project team determined that an aluminum building was not the best option due to higher-than-anticipated costs and concerns with corrosion from the station's salt spray environment, which could result in leaks at the building seams.

 

The project team determined that a building constructed with tip-up concrete walls and mortar would provide better protection for the station environment and better serve the Utility's long-term needs. This change in building material required a redesign of the project, including additional architectural, mechanical, and electrical engineering services from Sargent & Lundy. As a result, construction was delayed while the building design and associated specifications were revised.

 

The change in scope will delay the contract date to December 31, 2027.

 

FISCAL IMPACT:

There is not a direct fiscal impact associated with this Change Order as it extends the contract but does not change the value of the awarded contract.