File #: 26-0051    Version: 1
Type: Procurement Change Order Status: Agenda Ready
File created: 1/13/2026 In control: City Council
On agenda: 2/3/2026 Final action:
Title: Approve the award of Change Order #1 to Contract 24-212, Fairway and Country Lakes Water Main Improvements, to Bluewater Construction, LLC for an amount not to exceed $117,422.19, for a total award of $1,502,422.19 and for an additional 61 days
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #1 to Contract 24-212, Fairway and Country Lakes Water Main Improvements, to Bluewater Construction, LLC for an amount not to exceed $117,422.19, for a total award of $1,502,422.19 and for an additional 61 days

body

 

DEPARTMENT:                      Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

On February 18, 2025, the City Council awarded Bid 24-212 to Bluewater Construction, LLC for an amount not to exceed $1,385,000.00 to install water mains within existing easements at Fifteen 98 Apartments adjacent to Fairway Drive and Autumn Run Apartments adjacent to Country Lakes Drive.

 

The contract included a completion date of October 31, 2025.

 

DISCUSSION:

Unforeseen site conditions beyond the contractor’s control necessitate this Change Order which includes final balancing changes reflecting as-built quantities for the contract pay items along with extra work items deemed necessary to ensure a successful project.  The major extra work items include reconfigurations at several water main connections, changes to patching methods and remobilization costs resulting from delays outside the contractor’s control.  

 

Contract Award

Original Contract Value

$ 1,385,000.00

Prior Cumulative Approved Change Orders 

$ 0.00

Subtotal

$ 1,385,000.00

(+/-) This Change Order

$ 117,422.19

Total Contract Value

$ 1,502,422.19

 

Additionally, due to delays related to the City acquiring the necessary temporary easements at the Autumn Run Apartments, which was beyond the contractor’s control, an extended completion date was required.  To complete this additional work, staff requests a revised completion date of December 31, 2025.

 

FISCAL IMPACT:

CIP #: WU424 - Fairway and Country Lakes Water Main Improvements

 

The change order will be charged to the Infrastructure account listed below. The 2025 Budget included $2,583,945 in this account for the completion of this project, with $1,290,383.44 spent thus far. With the amount not to exceed $117,422.19, the change order and total award amount remain within the 2025 Budget.

 

Account Number

Fund Description

Total Budget

41251500-551502

Water Utilities Fund

$68,654,488