File #: 24-0077    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 1/16/2024 In control: City Council
On agenda: 2/6/2024 Final action: 2/6/2024
Title: Approve the award of JOC Procurement 19-013-2.B.00-DPW, Municipal Center Lobby Security Improvements, to Robe Construction, Inc. for an amount not to exceed $296,384, plus a 5% contingency

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of JOC Procurement 19-013-2.B.00-DPW, Municipal Center Lobby Security Improvements, to Robe Construction, Inc. for an amount not to exceed $296,384, plus a 5% contingency

body

 

DEPARTMENT:                     Department of Public Works

 

SUBMITTED BY:                     Richard Dublinski, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The Municipal Center is home to nine departments, including the Mayor and City Council offices, and approximately 220 employees. While residents, vendors, and guests can access other City facilities, the Municipal Center remains the most visited site.

 

Built in 1991, the Municipal Center is experiencing age-related issues, application of outdated technology, and is in need of security improvements. To address these issues, in 2022, the Department of Public Works - Public Building Operation (DPW-PBO) contracted Kluber Architects and Engineers to perform an evaluation and develop a multi-year project plan to renovate and enhance building efficiency and security.

 

Phase I includes the installation of security improvements to the main lobby entrance.

 

DISCUSSION:

The Municipal Center lobby security project consists of constructing a dedicated security office space adjacent to the vestibule at the main entrance. The work shall include card access at the new interior doorways, as well as remote door unlocking from the guard station. There will be a continuous countertop with two individual workstations and two computer terminals in the office space. A transaction window and talk through will be installed in the existing glass to allow the guard to greet and direct visitors. The station room will be open to the balance of the lobby. Please see the rendering below.

 

 

Due to the multiple trades involved with the project, DPW-PBO recommends using the City’s Job Order Contracting (JOC) contractor, Robe Inc.

 

Term of contract is from date of award through August 1, 2024.

 

FISCAL IMPACT:

CIP #: MB222 - Municipal Center Improvements

 

Improvements to the Municipal Center is expensed to the account number listed below. A total of $340,000 is approved for this project as part of the Capital Improvement Program for work related to CIP MB222. The requested award, including the contingency amount is within the budget.

 

Account Number

Fund Description

Total Budget Amount

31342200-551500

Capital Projects Fund

$2,645,700

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.