File #: 22-1415    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 11/14/2022 In control: City Council
On agenda: 12/6/2022 Final action:
Title: Approve the award of Bid 22-310, Grand Pavilion and Covered Bridge Roof Replacements, to Filotto Roofing, for an amount not to exceed $133,500.00 plus a five percent contingency
Related files: 24-0455

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 22-310, Grand Pavilion and Covered Bridge Roof Replacements, to Filotto Roofing, for an amount not to exceed $133,500.00 plus a five percent contingency

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     William J Novack, Director/City Engineer

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

Per the terms of the Intergovernmental Agreement for maintenance of the Naperville Riverwalk, the City of Naperville is responsible for all capital maintenance improvements over $25,000.  Smaller-scale improvements are managed by the Naperville Park District as part of overall Riverwalk maintenance.

 

The roofs at the Grand Pavilion, and on the covered bridge adjacent to Fredenhagen Park, have reached the end of their useful lives.  Heavily worn sections of the covered bridge roof were replaced several years ago but now the entire 23-year old roof is in need of a complete replacement.

 

The covered bridge roof will be replaced with a similar cedar shake roof while the asphalt shingle roof of the Grand Pavilion will be replaced with a synthetic shingle.  The Riverwalk Commission has used the synthetic shingles on several other structures on the Riverwalk with great success.  None of these roofs have required any maintenance or replacement since installation, and some have been in place for over 15 years.

 

In October 2022, the TED Business Group on behalf of the Naperville Riverwalk Commission, issued Bid 22-310, Grand Pavilion and Covered Bridge Roof Replacements for pubic bid. 

 

DISCUSSION:

 

Advertisement Date:

10/20/2022

Notices Sent:

295

Opening Date:

11/9/2022

Planholders:

25

 

 

Proposals Received:

1

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Cost

Engineer’s Estimate

$156,000

Filotto Roofing

$133,500.00

 

While only one bid was received it was below the engineer’s estimate.  Staff believes the single bid is due to the type of roofing materials specified and the time of year.  Both specified shingles require roofing contractors who are qualified to install these materials.  The Riverwalk Commission considered using a more popular shingle, but the covered bridge would lose its aesthetic appeal.  Even though the cedar shakes require maintenance and replacement over time it is those shingles that define our covered bridges. 

 

While the synthetic shingles cost more than a traditional asphalt shingle, our experience has shown that these shingles last considerably longer and require less maintenance.  The additional up-front cost and limited bidders is worth the greater performance of this material.

 

The completion date of this project is April 29, 2023.   

 

FISCAL IMPACT:

CIP#: PA051

 

Per the agreement between the City of Naperville and the Naperville Park District, the City is responsible for capital improvements that have a cost over $25,000. Replacement of the Grand Pavilion and Covered Bridge roofs were included in the 2022 budget, which included $170,000 for Riverwalk capital projects, including PA051. The requested award is within budget.

 

Account Number

Fund Description

Proposed Budget Amount

30144000-531302

Food and Beverage

$186,085

30292200-551502

Capital Projects

$50,000