ACTION REQUESTED:
title

Approve the award of Option Year One to Contract RFP 16-353, Consulting Engineering Services for Soils and Materials Testing, to Midland Standard Engineering for an amount not to exceed $120,000

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     William J. Novack, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The services of a soils and materials testing consultant is required by Transportation, Engineering and Development Business Group, Department of Public Works and Water Utilities every year to perform quality assurance testing for hot-mix asphalt, concrete and other materials that are used through the City’s construction contracts.  These services include performing soils and materials testing in connection with public improvement construction, MFT funded projects, new development and infrastructure construction type projects. 

 

On January 17, 2017, the City Council approved RFP 16-353 for Midland Standard Engineering to perform soils and materials testing.  The contract was for a period of two years ending December 31, 2018, with consideration for three one-year options to renew. 

 

DISCUSSION:

Midland has provided good service during the initial term of the contract and has agreed to renew the contract for an additional year. The contract allows for a maximum percentage increase of 1.05% in the option years.  Staff was able to negotiate a zero percent increase for the first option year.

 

The term of the first extension is January 1, 2019 through December 31, 2019, with two one-year option years remaining.

 

FISCAL IMPACT:

CIP #: MP004, MP 009, WU04, WU10, WWU42

 

Soil and material testing services are expensed to the accounts listed below. Funding for this work is budgeted in the Capital Projects Fund ($85,000), Water Utilities Fund ($30,000) and General Fund ($5,000). The requested award of $120,000 is within the budgeted amount for this expense.

 

Account Number

Fund Description

Total Budget Amount

30282200-551502

Capital Projects

$7,913,000

41251500-551502

Water Utilities

$11,576,000

31251100-531309

General

$10,000