File #: 25-0738    Version: 1
Type: Procurement Award Status: Agenda Ready
File created: 5/22/2025 In control: City Council
On agenda: 6/3/2025 Final action:
Title: Approve the award of Bid 25-016, 2025 Street Resurfacing Program - Local, to K-Five Construction Corporation for an amount not to exceed $2,942,489.95 plus a 3% contingency
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 25-016, 2025 Street Resurfacing Program - Local, to K-Five Construction Corporation for an amount not to exceed $2,942,489.95 plus a 3% contingency

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     Jennifer Louden, Director of TED

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The Transportation, Engineering, and Development Business Group (TED) issued Bid 25-016 seeking contractors to resurface approximately 3.12 miles of various roadways. This work also includes the removal and replacement of approximately 11,100 linear feet of curb and gutter along Naper Blvd between Chicago Ave and Plank Rd. This section of roadway will not be resurfaced at this time, but is currently scheduled for resurfacing within the next five years.

 

The City currently maintains approximately 475 centerline miles of road through the annual Street Maintenance Improvement Program (MIP). An important component of the MIP is the resurfacing program which ensures City streets remain in good condition for the movement of traffic while also protecting the integrity of the roadway base. When resurfacing is delayed, the roadway base begins to deteriorate prematurely, resulting in the need for costly and disruptive road reconstruction projects.

 

TED will conduct two street resurfacing programs this year. The first program, using state motor fuel tax (MFT) funds, was awarded in April 2025. The second program uses City funds and is the subject of this request.

 

DISCUSSION:

 

Advertisement Date:

4/22/2025

Notices Sent:

223

Opening Date:

5/21/2025

Planholders:

28

 

 

Proposals Received:

3

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Cost

K-Five Construction Corporation

$2,942,489.95

Engineer’s Estimate

$3,296,243.00

A Lamp Concrete Contractors Inc

$3,474,953.50

R.W. Dunteman Company

RESCINDED

 

R. W. Dunteman Co. was the low bidder at the time of the bid opening. However, the contractor informed the City of an error in one of the unit prices. Due to this error, R. W. Dunteman rescinded the bid offer.

 

Staff recommends K-Five Construction Corp for the award as the lowest responsive and responsible bidder for the procurement of construction services, as defined by Section 1-9B-7 of the Procurement Code (RBO-qualified). K-Five has performed street resurfacing work through both the City’s MFT and Local funded programs since 2021.

 

The completion date of this project is October 27, 2025. 

 

FISCAL IMPACT:

CIP #: MP009

 

Street resurfacing is one component of the overall award for the annual Street Maintenance Improvement Program (MP009). The 2025 budget includes $12,000,000 for all components of MP009. The chart below breaks out the various award components and award timeframes for the MIP.

 

Name

Bid No.

Award Amount

Status

Resurfacing - MFT

25-015

$5,563,599.47

Awarded 4/2/25

Resurfacing - Local

25-016

$2,942,489.95

Recommend for award 6/3/2025

Crackfilling

25-017

$546,975.32

Awarded 4/15/2025

Patching

25-018

$542,825.00

Awarded 4/15/2025

Micro-surfacing

25-019

$733,615.00

Recommend for award 6/3/2025

Sidewalk R&R for Micro-surfacing

25-022

$194,174.40

Awarded 4/2/25

Pavement Marking

25-020

$25,000.00

Awarded 3/18/25

Total to date:

 

$10,548,679.14

 

 

The 2025 Street Resurfacing Program - Local is expensed to the Infrastructure account listed below. TED budgeted $3,400,000 for this program in 2025. The award requested is within the amount budgeted for this expense.

 

Account Number

Fund Description

Total Budget Amount

30282400-551502

Road & Bridge Fund

$3,500,00

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.