File #: 21-1037    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 8/4/2021 In control: City Manager Procurement Awards
On agenda: 9/1/2021 Final action:
Title: Approve the award of Change Order 1 to Contract 21-163, Springbrook Water Reclamation Center Structural Engineering, to Deuchler Engineering Corporation for an amount not to exceed $13,150 and for a total award of $42,194
Attachments: 1. WW041
Related files: 21-0549
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY MANAGER AUTHORITY PROCUREMENT AWARDS

 

ACTION REQUESTED:
title

Approve the award of Change Order 1 to Contract 21-163, Springbrook Water Reclamation Center Structural Engineering, to Deuchler Engineering Corporation for an amount not to exceed $13,150 and for a total award of $42,194

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BACKGROUND:

In April 2021, the City Manager awarded Contract 21-163 to Deuchler Engineering Corporation for the structural evaluation and engineering design of five structural engineering tasks at Springbrook Water Reclamation Center. The engineering tasks include evaluation of a conveyor in the biosolids holding building, knock out panels in the aeration tanks, settlement of the aeration tank walkway and leakage around the influent channel, as well as preparation of a preliminary report, engineer’s opinion of probable construction cost and a final report including design details, drawings and specifications suitable for inclusion in a construction bid contract package.

 

The value of the original contract was $29,044.

 

DISCUSSION:

The consultant performed well on the structural evaluation and engineering design work. Due to existing heavy workload of the city’s engineering staff, staff solicited a price for construction services from the consultant. The construction services tasks include:

 

                     Additional meetings, including a pre-bid conference, pre-construction meeting, construction progress meetings as requested

                     Time spent preparing addenda and revisions to plans and specifications

                     Shop drawing reviews of all submittals, including structural steel, concrete mix design and polyurethane injection grout

                     Field visits as requested and including punchlist and final inspection

                     Responding to RFIs during construction.

 

For the items outlined above, staff recommends approval of Change Order 1 in an amount not to exceed $13,150.

 

FISCAL IMPACT:

CIP: WW041

 

Consultant services for structural repair projects at Springbrook Water Reclamation Facility are expensed to the infrastructure account listed below, as part of the capital improvement program. A total of $415,950 is budgeted for WW041 in 2021. The requested award is within budget.

 

Account Number

Fund Description

Total Budget Amount

41251500-551502

Water & Wastewater Fund

$26,743,950