CITY COUNCIL AGENDA ITEM
ACTION REQUESTED:
title
Approve the award of Bid 23-117, SWRC Centrifuge Control Panel Replacement Phase I and Polymer Feed System Replacement, to Connelly Electric Company, for an amount not to exceed $242,000 plus a 5% contingency
body
DEPARTMENT: Water Utilities
SUBMITTED BY: Darrell Blenniss, Director
BOARD/COMMISSION REVIEW:
N/A
BACKGROUND:
The centrifuges and polymer feed systems at the Springbrook Water Reclamation Center (SWRC) were installed in 1995 as part of the Phase II expansion. One of the two centrifuge control panels and one of the polymer feed systems have reached the end of their usable service life and need to be replaced. Both components are critical to the dewatering and solids operation at SWRC. The purpose of the polymer feed system is to inject polymer to mix with the sludge to create larger solid flocs that make it easier for separation and dewatering. The centrifuge control panel is what controls the centrifuge and crucial for the power of the unit.
In May 2024, the Water Utilities issued Bid 23-117, SWRC Centrifuge Control Panel Replacement Phase I and Polymer Feed System Replacement, which includes the removal and installation of a new centrifuge control panel, removal and installation of a new polymer feed system and associated SCADA improvements. The work also includes the installation of associated electrical conduits, wires and concrete pads.
DISCUSSION:
Advertisement Date: 5/31/2024 Notices Sent: 438
Bid Opening Date: 7/9/2024 Planholders: 17
Proposals Received: 2
Bids were received from the following vendors:
Vendors Name |
Proposed Cost |
Connelly Electric Company |
$242,000 |
Engineer’s Estimate |
$300,000 |
Dahme Mechanical Industries |
$358,888 |
Connelly Electric Company has completed several successful projects for the City in the past, and staff is confident in their ability to perform the work as specified.
The term of the contract is from the date of award through the anticipated completion date of December 15, 2025.
FISCAL IMPACT:
CIP #: WW044 - SWRC Miscellaneous Process-related Replacements/Upgrades
Replacement and/or rehabilitation of process related components and equipment is expensed to the account number listed below. The 2024 budget included $735,700 for this project, of which $173,382 has been spent. The 5-year (2024-2028) CIP includes an estimated $1.6M related to this project. The requested award is accommodated within the budget.
Account Number |
Fund Description |
Total Budget Amount |
41252000-551502 |
Water Capital Fund |
$40,264,902 |
*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.