File #: 25-0690    Version: 1
Type: Procurement Change Order Status: Agenda Ready
File created: 5/15/2025 In control: City Council
On agenda: 6/3/2025 Final action:
Title: Approve the award of Change Order #1 to RFQ Work Order 22-109-0.A.00-WU, Springbrook Water Reclamation Center Biosolids Holding Tank Phase II Engineering Services, to Donohue & Associates, Inc. for an amount not to exceed $36,800, a total award of $220,210, and an additional 379 calendar days
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #1 to RFQ Work Order 22-109-0.A.00-WU, Springbrook Water Reclamation Center Biosolids Holding Tank Phase II Engineering Services, to Donohue & Associates, Inc. for an amount not to exceed $36,800, a total award of $220,210, and an additional 379 calendar days

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

On February 20, 2024, the City Council awarded contract 22-109.A00-WU Springbrook Water Reclamation Center Biosolids Holding Tank Phase II Engineering Services to Donohue & Associates, Inc.  The work includes design engineering, permitting, bid phase and construction services for the installation of a new 500,000-gallon biosolids holding tank and associated conveyance systems.

 

DISCUSSION:

Currently, the project is under construction, and City staff is performing in-house construction management. However, certain tasks, such as rebar inspection and concrete placement inspection require a licensed professional structural engineer, which the City does not have on staff. Therefore, City staff has requested Donohue & Associates to expand their scope and fees to provide these services.

 

Additionally, the current contract is set to expire on April 30, 2026. Since construction is expected to be completed on May 14, 2027, staff recommends an extension of the contract to ensure construction support services are available for the full duration of the project.

 

FISCAL IMPACT:

CIP#: WW042 - SWRC Biosolids Holding Tank - Phase II

 

The requested award is expensed to the account number listed below. The fee for the additional scope is $36,800, increasing the total contract amount to $220,210. The additional fee exceeds the budget for the project for the current year. However, it can be accommodated through a project of similar cost that was included in the budget and not needed in 2025.  Staff will monitor expenditures to ensure they remain within the approved budget.

 

Account Number

Fund Description

Total Budget Amount

41251500-551502

Water Utilities Fund

$68,654,488