File #: 20-515    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 4/24/2020 In control: City Council
On agenda: 5/19/2020 Final action: 5/19/2020
Title: Approve the award of Bid 20-072, Southeast Waterworks Improvements, to Dahme Mechanical Industries for an amount not to exceed $304,775, plus a 5% contingency
Related files: 17-852, 20-1515

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 20-072, Southeast Waterworks Improvements, to Dahme Mechanical Industries for an amount not to exceed $304,775, plus a 5% contingency

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The Water Utilities’ Southeast Waterworks pump station, located at 1699 Ranchview Drive, houses three booster pumps. Boosters pumps provide sufficient flows and pressure to the City’s water distribution system for domestic and emergent fire flow usage. The original three booster pumps were installed approximately 40 years ago.

 

In 2018, booster pumps 1 and 2 were replaced. Currently, booster pump 3 is no longer operational and out of service. Due to the age of pump 3 and condition of the internal operating parts, staff has determined that the pump needs to be replaced. The new pump will ensure Southeast Waterworks has adequate pump capacity to provide sufficient fire flows to the service area. The project cannot be deferred because of fire protection safety concerns.

 

In March 2020, the Water Utilities issued Bid 20-072, Southeast Waterworks Improvements, to replace water booster pump 3. The work also includes replacing existing control valves, butterfly valves, pressure gauges and piping in the valve room.

 

DISCUSSION:

 

Advertisement Date: 03/06/2020                                                               Notices Sent:  473

         Opening Date: 04/27/2020                                                                Planholders:    12

                                                                                                                                       Bids Received:     3

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Cost

Engineer’s Estimate

$300,185

Dahme Mechanical Industries

$304,775

R. J. O’Neil Inc.

$314,000

Independent Mechanical Industries Inc.

$347,750

The completion date of the project is January 31, 2021.

FISCAL IMPACT:

CIP: WU007

 

Water pump replacements are expensed to the infrastructure account listed below as part of the capital improvement program. A total of $1,000,000 is budgeted for WU007 in 2020. The requested award is within budget.

 

Account Number

Fund Description

Total Budget Amount

41251500-551502

Water and Wastewater

$12,119,788

 

Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.