File #: 23-0290    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Agenda Ready
File created: 3/7/2023 In control: City Council
On agenda: 3/21/2023 Final action:
Title: Approve the award of Bid 23-015, T10 McDowell Trunk Sewer Rehabilitation Phase 2, to Hoerr Construction Inc. for an amount not to exceed $810,403, plus a 3% contingency
Attachments: 1. WW051

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 23-015, T10 McDowell Trunk Sewer Rehabilitation Phase 2, to Hoerr Construction Inc. for an amount not to exceed $810,403, plus a 3% contingency

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The T10 McDowell Trunk Sewer transfers wastewater from the northwest portions of the city to the Northwest Pump Station at 511 N. River Road. In 2020, the Water Utilities performed an internal condition assessment of this asset and discovered many areas of pipe deterioration, cracks, and groundwater leaks. Also, all manholes related to the trunk sewer were inspected and are in the same condition as the trunk sewer.

 

In February 2023, the Water Utilities issued Bid 23-015, T10 McDowell Trunk Sewer Rehabilitation Phase 2. The contractor will rehabilitate 3,802 feet of existing 24-inch reinforced concrete pipe sanitary trunk sewer by installing resin-saturated felt lining cured with steam or hot water (CIPP) as per ASTM F1216-09. The finished product is a monolithic structural pipe formed to the existing host pipe.

 

The bid also includes the rehabilitation of 15 sanitary sewer manholes and the chemical grouting of four service laterals. This work is to be done in conjunction with CIPP lining.

 

The T10 McDowell Trunk Sewer Rehabilitation Phase 2 project is part of the City’s IEPA required ten-year wastewater collection rehabilitation plan, as well as the IEPA required ten-year infiltration and inflow reduction plan to reduce wastewater backups during heavy rain events.

 

DISCUSSION:

Advertisement Date: 2/10/23                                                      Notices Sent: 263

Bid Opening Date:    3/2/23                                                        Planholders: 19

                                                                                                    Proposals Received: 5

Proposals were received from the following vendors:

Firm Name

Proposed Cost

Hoerr Construction Inc.

$810,403

Visu-sewer

$839,197

Engineers Estimate

$1,222,100

Lanzo Construction Company

$1,394,795

Insituform

$1,394,870

National Power Rodding

$3,200,200

 

 

 

FISCAL IMPACT:

CIP# WW051 - McDowell Rd Trunk (T10) Sewer Rehab

 

Rehabilitation cost of the T10 trunk sewer is expensed to the account number listed below as part of the FY23 Capital improvement program. A total of $1.5 million is budgeted for this project. The requested award including the 3% contingency is within the budget.

 

Account Number

Fund Description

Total Budget Amount

41252000-551502

Water Capital

$39,813,900

 

Per Council directive, contingency on construction projects is set at 3% on projects over

$500,000 and 5% on projects under $500,000.