Skip to main content
File #: 25-1708    Version: 1
Type: Procurement Award Status: Agenda Ready
File created: 12/29/2025 In control: City Council
On agenda: 1/20/2026 Final action:
Title: Approve the award of Bid 25-196, South Operation Center Generator Replacement, to Omega Electric DBA Temperature Service Company, Inc. for an amount not to exceed $1,599,000 plus a 3% contingency
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 25-196, South Operation Center Generator Replacement, to Omega Electric DBA Temperature Service Company, Inc. for an amount not to exceed $1,599,000 plus a 3% contingency

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The existing generator at the South Operations Center (SOC) was installed in the 1970s as part of the original facility development. It has reached the end of its service life and replacement parts are no longer available. In addition, due to changes in demand, the generator is now undersized and requires replacement.

 

On November 7, 2025, the Water Utilities issued Bid No. 25-196 for the SOC Generator Replacement Project. The project includes replacement of the existing generator, the automatic transfer switch (ATS), associated electrical conduits and wiring, and upgrades to the supervisory control and data acquisition (SCADA) system.

 

The project scope also includes installation of a concrete generator pad, a wood fence, and related site improvements.

 

DISCUSSION:

 

Advertisement Date:

11/07/2025

Notices Sent:

163

Opening Date:

12/19/2025

Planholders:

20

 

 

Proposals Received:

1

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Cost

Omega Electric

$1,599,000.00

Engineer’s Estimate

$1,969,100.00

 

Even though only one bid was received from Omega Electric DBA Temperature Service Company, Inc., the bid price is below the engineer’s construction cost estimate. In addition, staff reviewed Omega Electric’s reference projects, and they are an experienced contractor that has completed similar projects for other municipalities.

 

Staff recommends Omega Electric DBA Temperature Service Company, Inc. for the award as the responsive and responsible bidder for the procurement of construction services, as defined by Section 1-9B-7 of the Procurement Code (RBO-qualified).

 

The term of the contract is from the date of award through the anticipated completion date of May 31, 2027.

 

FISCAL IMPACT:

CIP #: WW085 - South Operation Center (SOC) Generator Replacement

 

The SOC Generator Replacement Project is expensed to the Infrastructure account listed below. The project was budgeted at $1,135,000 for 2026, with an additional $1,015,000 planned for 2027.  The allocated funds for 2026 are sufficient, and the department will ensure 2027 funds are budgeted appropriately.

 

Account Number

Fund Description

Total Budget Amount

41251500-551502

Water Utilities Fund

$86,910,285

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.