Title: Approve the award of Change Order #1 to Contract 24-198, Ogden Avenue and Washington Street Water Main Improvements, to Scanlon Excavating and Concrete for an amount not to exceed $343,347.75, for a total award of $5,223,287.25 and for an additional 238 days
Attachments: 1. CO#1 -2025 ADDITIONAL WORK-R1
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #1 to Contract 24-198, Ogden Avenue and Washington Street Water Main Improvements, to Scanlon Excavating and Concrete for an amount not to exceed $343,347.75, for a total award of $5,223,287.25 and for an additional 238 days

body

 

DEPARTMENT:                      Water Utilities

 

SUBMITTED BY:                      Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

On February 18, 2025, City Council awarded Bid 24-198 to Scanlon Excavating and Concrete for an amount not to exceed $4,879,939.50 to install water main on Ogden Avenue between Washington Street and Wright Street and on Washington Street between Ogden Avenue and Bauer Road. 

 

The contract included a completion date of October 31, 2025.

 

DISCUSSION:

Unforeseen site conditions, as well as additional work required to ensure the project’s successful completion, necessitate this Change Order. The extra work included, but was not limited to, remediation of a leaking underground storage tank, removal of contaminated soil, and directional drilling difficulties at certain locations due to underground obstacles. Complete details are listed in the attached Change Order.

 

Contract Award

Original Contract Value

$ 4,879,939.50

Prior Cumulative Approved Change Orders 

$ 0.00

Subtotal

$ 4,879,939.50

(+/-) This Change Order

$ 343,347.75

Total Contract Value

$ 5,223,287.25

 

To complete the work items outlined, staff granted an additional 38.5 working days. The contractor remobilized on May 18, 2026, making a revised completion date of June 25, 2026 and a total project extension of 238 days.

 

FISCAL IMPACT:

CIP #: WU403 - Ogden and Washington Water Main Improvements

 

The Ogden Avenue and Washington Street Water Main Improvements CIP is expensed to the Infrastructure account listed below as part of the Water Utilities’ capital program.  A total of $2,000,000 is budgeted for the project in the 2026 Budget, of which $611,942 has been spent thus far. The requested award of $343,347.75 is within budget.

 

Account Number

Fund Description

Total Budget

41251500-551502

Water Utilities

$86,910,285