File #: 21-0681    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 5/18/2021 In control: City Council
On agenda: 6/1/2021 Final action: 6/1/2021
Title: Approve the award of Bid 21-190, 5th Avenue Bridge over Cress Creek, to MYS, Incorporated, for an amount not to exceed $138,330.50, plus a 5% contingency
Attachments: 1. CIP PAGE
Related files: 21-1665

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 21-190, 5th Avenue Bridge over Cress Creek, to MYS, Incorporated, for an amount not to exceed $138,330.50, plus a 5% contingency

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     William J. Novack, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

5th Avenue carries one lane of traffic in each direction and is a neighborhood connector roadway under the jurisdiction of the City of Naperville. General features of the surrounding area are adjacent residential housing, a forest preserve, and a fire station.

The 5th Avenue Bridge was originally constructed in 1980 and consists of a single span structure with an overall length of 18 feet 6 inches.

The bridge was inspected by City staff in September 2018 and again one month later in October. Based on the findings, staff recommended a follow-up load rating inspection and calculation be conducted. Staff concluded that the superstructure of the 5th Avenue Bridge should be replaced and, due to its deteriorating condition, the bridge has since been load posted allowing only certain weighted vehicles to traverse as well as put on a six-month inspection schedule.

 

DISCUSSION:

 

Advertisement Date:

05/04/2021

Notices Sent:

111

Opening Date:

05/19/2021

Planholders:

  20

 

 

Proposals Received:

    9

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Cost

MYS Incorporated

$138,330.50

PT Ferro Construction

$181,307.60

Herlihy Mid-Continent Company

$184,989.00

Alliance Contractors, Incorporated

$205,135.30

Engineer’s Estimate

$206,300.00

Baumgartner Construction, Incorporated

$211,862.00

Lorig Construction Company

$220,623.35

Copenhaver Construction

$284,493.10

Areatha Construction Company, Incorporated

$333,969.30

D Construction

$334,595.00

 

The low bid is 24% lower than next lowest bidder and significantly lower than the engineer’s estimate. The low bidder is on the Illinois Department of Transportation (IDOT) prequalified list of contractors to perform all work within the contract. Staff contacted the bidder and confirmed they can perform the identified work for the amount bid.

 

The completion date of this project is 8/19/2021.

 

FISCAL IMPACT:

CIP #: BR033

 

5th Avenue Bridge is expensed to the Infrastructure account listed below.  This work is related to BR033, 5th Avenue Bridge Improvement, of which $200,000 was budgeted for in 2021.  The requested award is within the budgeted amount for this expense.

 

Account Number

Fund Description

Total Budget Amount

30282300-551502

Bond Fund

$9,243,000

 

 

 

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.