File #: 21-1085    Version: 1
Type: Procurement Award Status: Passed
File created: 8/17/2021 In control: City Council
On agenda: 9/7/2021 Final action: 9/7/2021
Title: Approve the award of Bid 21-275, Springbrook Water Reclamation Center 2021 Structural Repairs, to Crossroads Construction, Inc. for an amount not to exceed $130,000 plus a 5% contingency
Attachments: 1. WW041
Related files: 22-0067

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 21-275, Springbrook Water Reclamation Center 2021 Structural Repairs, to Crossroads Construction, Inc. for an amount not to exceed $130,000 plus a 5% contingency 

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

In April 2021, the Water Utilities issued RFQ 21-163 for a consulting firm to provide technical assistance and engineering design for a number of structural engineering repairs at Springbrook Water Reclamation Center.  

 

In August 2021, the Water Utilities issued Bid 21-275, Springbrook Water Reclamation Center 2021 Structural Repairs. The scope of this project includes constructing a new biosolids conveyor support structure, foundations, and pushwall; demolishing the existing conveyor supports and restoring the concrete paving; sealing of two existing knockout panels on the aeration tanks and repair of aeration tank expansion joint.

 

An additive alternate is included for the demolition and replacement of the concrete walkway at the aeration tanks and will be included in the total award due to favorable pricing received for the alternate.

 

DISCUSSION:

 

Advertisement Date: 8/13/2021                                                     Notices Sent: 120

   Bid Opening Date: 8/30/2021                                            Planholders: 12

                                                                                                                              Proposals Received: 3

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Cost

Alternate Proposed Cost

Crossroad Construction, Inc.

$105,000

$25,000

Keno & Sons Construction Company

$199,500

$72,200

Engineers Estimate

$221,250

$31,900

Vixen Construction, Inc.

$269,815

$34,306

 

Water Utilities has not worked with this contractor in the past.  Results of the reference were satisfactory; and the vendor is registered and in good standing with the Illinois Secretary of State.

 

The contract completion date for this project is December 31, 2021.

 

FISCAL IMPACT:

CIP: WW041

 

Springbrook Water Reclamation Center 2021 Structural Repairs are expensed to the Infrastructure account below. A total of $415,950 is budgeted in 2021 for WW041 - Springbrook Water Reclamation Center Facility Replacements. The proposed award is within budget.

 

Account Number

Fund Description

Total Budget Amount

41251500-551502

Infrastructure

$26,743,950

 

Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.