File #:
|
24-1222
Version:
1
|
|
|
Type:
|
Procurement Award
|
Status:
|
Passed
|
On agenda:
|
12/3/2024
|
Final action:
|
12/3/2024
|
Title:
|
Approve the award of Bid 24-210, Royal Oaks Water Main Improvements, to Bluewater Construction LLC for an amount not to exceed $1,495,000 plus a 3% contingency
|
CITY COUNCIL AGENDA ITEM
ACTION REQUESTED: title
Approve the award of Bid 24-210, Royal Oaks Water Main Improvements, to Bluewater Construction LLC for an amount not to exceed $1,495,000 plus a 3% contingency
body
DEPARTMENT: Water Utilities
SUBMITTED BY: Darrell Blenniss, Director
BOARD/COMMISSION REVIEW: N/A
BACKGROUND:
In support of the City’s priority to provide utility services that are reliable and safe, in September 2024, the Water Utilities issued Bid 24-210, Royal Oaks Water Main Improvements. The project includes the replacement of the water main on White Oak Drive, Elizabeth Avenue and Anne Road in the Royal Oaks Subdivision.
The purpose of the project is to replace aging and deficient water main on these streets. The existing 6-inch cast iron water main was installed in the 1960’s and it will be replaced and upsized to 8-inch ductile iron pipe in accordance with City standards.
DISCUSSION:
Advertisement Date: |
9/25/2024 |
Notices Sent: |
286 |
Opening Date: |
10/18/2024 |
Planholders: |
43 |
|
|
Proposals Received: |
12 |
Bids were received from the following vendors:
Vendor Name |
Base Bid |
Bid Alternate A |
Bluewater Construction, LLC |
$1,495,000.00 |
$1,465,000.00 |
J Congdon Sewer Service |
$1,524,984.50 |
$1,460,324.50 |
Performance Construction & Engineering |
$1,626,919.00 |
$1,534,203.00 |
A Lamp Concrete Contractors |
$1,638,952.00 |
$1,588,989.00 |
Everlast Blacktop |
$1,826,201.54 |
$1,747,749.54 |
Cerniglia Co |
$1,828,433.15 |
$1,754,331.67 |
Acqua Contractors Corp |
$1,852,000.00 |
$1,760,000.00 |
H Linden & Sons Sewer and Water, Inc. |
$1,892,553.00 |
$1,892,553.00 |
Winninger Excavating, Inc |
$1,926,848.00 |
$1,839,264.00 |
Bolder Contractors |
$2,068,170.00 |
$2,032,510.00 |
Copenhaver Construction, LLC |
$2,144,284.00 |
$2,067,964.00 |
Martam Construction, Inc |
$2,487,776.00 |
$2,440,976.00 |
Engineer’s Estimate |
$2,501,550.00 |
$2,323,250.00 |
The bid documents for this project included a Base Bid to obtain pricing for ductile iron water main pipe and Bid Alternate A to obtain pricing for PVC water main pipe. After evaluating the submitted bids, staff determined that selecting the lowest Base Bid was in the best interest of the City. Ductile iron is the City’s standard water main material, and while PVC has been used in recent years due to substantial cost savings, the cost of ductile iron is once again competitive.
Bluewater Construction submitted the lowest base bid for the project at $1,495,000. The low bid is 50% lower than the budgeted amount of $2,983,977.
Water Utilities staff based the 2024 budget on the average per-foot cost for the last several years. A favorable bidding environment and the timing of advertisement appear to contribute to the highly competitive bids received.
Staff believes the low bid submitted is reasonable for performing the work as specified. Upon checking the references provided, staff finds them to be a capable contractor.
The completion date for this project is October 31, 2025.
FISCAL IMPACT:
CIP #: WU407 - Royal Oaks Water Main Replacement
This project is included in the Water Utilities Capital Improvement Program. The 2025 proposed budget includes $2.93 million for this project, with a total project budget of $2.98 million over two years. Pending City Council approval, the requested award, including the contingency, is $1.44 million under budget.
Account Number |
Fund Description |
Proposed Budget |
41251500-551502 |
Water Utility Fund |
$68,654,488 |
*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.
|