ACTION REQUESTED:
title

Waive the applicable provisions of the Naperville Procurement Code and award Procurement 26-244, Water Utilities Cost-of-Service Rate Study and Financial Plan to Carollo Engineers, Inc. for an amount no to exceed $104,240

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

Approval of the award for 26-244 requires a waiver of Section 1-9B-4 (Methods of Source Selection) of the Naperville Procurement Code.  In 2024, Water Utilities (Utilities) partnered with Carollo Engineers, Inc. to provide a comprehensive water and wastewater cost of service rate and fee study.  The project developed a three-year financial plan, conducted a cost-of-service analysis, and developed rates to support the departmental work plan for 2025-2027.

 

Through that engagement, Carollo developed significant knowledge of the Utilities’ operations and financial structure, including the department budget, customer rate classes, consumption patterns, future growth projections, facilities plans, and debt position. The proposed study builds directly upon this existing work and requires the consultant to update and extend the financial and rate models developed during the prior engagement.

 

Given the specialized nature of the study, the continuity of the financial models and underlying data, and Carollo’s established knowledge of operations, transitioning this work to a new consultant would require duplicating significant efforts to become familiar with the City’s systems, assumptions, historical data, and prior recommendations. This would add time and potentially unnecessary costs to the project.

 

Additionally, Carollo’s successful completion of the prior study demonstrates ability to perform this specialized work and provide the City with an established consultant that can continue the analysis without a significant transition period.

 

For these reasons, staff recommends waiving the competitive source-selection requirements and awarding the three-year study to Carollo Engineers, Inc.

 

DISCUSSION:

The Cost-of-Service Rate Study and Financial Plan will include an update to Carollo’s rate model with new consumption data, and relevant trends in customer profiles.  It will also examine actual and budgeted operations and maintenance expenditures, CIP and planned funding sources, and actual and budgeted revenues.   Each of these will be forecasted over the three-year study period to ensure that revenues match expenses, cover existing debt obligations, and provide for necessary reserve fund balances.

 

The project will also perform a cost-of-service analysis to ensure that costs associated with each customer class are allocated proportionately in rates charged.  This analysis will use industry best practices as outlined in the American Water Works Association M1 Manual: Principles of Water Rates, Fee, and Charges, and Water Environment Federation’s Manual of Practice 27: Financing and Charges for Wastewater Systems.

 

Future rate structures and emerging trends for utility services that may impact rate design will be evaluated complete with an assessment of risks for each, the ratio of fixed to variable revenues, and cost of implementation.  An affordability assessment will be conducted, along with bill impacts for “typical” residential and non-residential customers.  Lastly, the project will also benchmark average bills charged by Naperville against peer utilities in the area. 

 

FISCAL IMPACT:

Cost of Service Modeling for Water and Wastewater will be expensed to the Other Professional Service account listed below.  The total cost of the award is $104,240, with $90,216 to be expended in the first year of the contract.  The remaining $14,024 will be used for annual updates to the model in 2029 and 2030 and will be budgeted accordingly at that time. 

 

Account Number

Fund Description

Proposed Budget

41101500-531309

Water Utilities

$160,000