Skip to main content
File #: 26-0279    Version: 1
Type: Procurement Change Order Status: Agenda Ready
File created: 2/25/2026 In control: City Council
On agenda: 3/18/2026 Final action:
Title: Approve the award of Change Order #1 to Contract 22-278, Springbrook Water Reclamation Center (SWRC) South Plant Return Activated Sludge (RAS) & Grit Improvements Project, to Donohue & Associates, Inc. for an amount not to exceed $70,000 and a total award of $923,000
Attachments: 1. Grit and RAS - Request for Additional Funding ESDC_epc
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #1 to Contract 22-278, Springbrook Water Reclamation Center (SWRC) South Plant Return Activated Sludge (RAS) & Grit Improvements Project, to Donohue & Associates, Inc. for an amount not to exceed $70,000 and a total award of $923,000

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

On December 6, 2022, the City Council awarded Contract 22-278, the Springbrook Water Reclamation Center South Plant RAS & Grit Improvements Project, to Donohue & Associates, Inc. The purpose of this contract is for Donohue & Associates, Inc. to provide engineering design, bidding assistance, and construction engineering services for the project.

 

The design and bidding assistance services have been completed. The construction engineering services are approximately 60% complete. The original scope of construction services included submittal reviews, responses to RFIs, and review of potential change order work.

 

DISCUSSION:

As the work has progressed, due to the complexity of the construction site, the consultant has been assigned additional tasks, including attending weekly progress meetings, document coordination and management, and coordination and communication with the City’s field representatives.

 

Accordingly, Donohue has submitted a Change Order that includes the additional scope of work described above, with an additional fee of $70,000. Staff met with Donohue’s team to review the proposed scope and associated fees. It was concluded that the additional scope of work and the associated fee are reasonable.

 

FISCAL IMPACT:

CIP #: WW048 - SWRC-South Plant RAS & Grit Improvements

 

The requested award will be charged to the Architect and Engineer Service account listed below. The project originally budgeted a $35,000 engineering fee for 2026. The requested Change Order exceeds the current year’s engineering budget for this project by $35,000. It is anticipated that this overage can be accommodated in the 2026 Budget, however staff will monitor expenditures to ensure they remain within the overall approved budget.

 

Account Number

Fund Description

Total Budget Amount

41251500-531301

Water Utilities Fund

$5,204,829