Title: Approve the award of Bid 24-013, 2024 Pavement Crackfill, to Denler Inc., for an amount not to exceed $404,717, plus a 5% contingency

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 24-013, 2024 Pavement Crackfill, to Denler Inc., for an amount not to exceed $404,717, plus a 5% contingency

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     William J. Novack, P.E., Director of Transportation, Engineering and Development/City Engineer

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

In March 2024, the Transportation, Engineering and Development (TED) Business Group issued Bid 24-013 seeking contractors to perform fiberized crackfilling on various city streets. Crackfilling consists of cleaning and sealing any cracks, voids, or joints two inches in width or less with asphalt cement reinforced by polypropylene fibers. It is a cost-effective preventative maintenance technique and when performed routinely, it can keep water and debris from getting into the pavement.

 

DISCUSSION:

 

Advertisement Date:

3/6/2024

Notices Sent:

55

Opening Date:

3/25/2024

Planholders:

13

 

 

Proposals Received:

2

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Cost

Engineer’s Estimate

$380,184.00

Denler, Inc.

$404,717.00

SKC Construction

$418,139.00

 

The final completion date of this project is July 13, 2024.

 

FISCAL IMPACT:

CIP #: MP009 - Street Maintenance Improvement Program (MIP)

 

Crack filling is one component of the overall award for MP009. The chart below breaks out the different award components and timeframes for the MIP.

 

Project Name

Bid No.

Award Amount

Status

Resurfacing - MFT North

24-023

$6,438,412.25

Awarded 4/2/24

Resurfacing - MFT South

24-019

 

Yet to be awarded

Crackfilling

24-013

$404,717.00

Recommend for Award 4/16/24

Patching

24-015

$531,785.00

Recommend for Award 4/16/24

Micro-surfacing

24-016

$753,484.29

Recommend for Award 4/16/24

Sidewalk R&R for Micro-surfacing

24-012

$402,875.40

Recommend for Award 4/16/24

Pavement Marking

24-001

 

Yet to be awarded

Total to date

 

$8,531,273.94

 

 

The 2024 Pavement Crackfill program is expensed to the Infrastructure account listed below. This is related to MP009, Street Maintenance Improvement Program (MIP) in which $13,000,000 is budgeted for 2024. Within the overall project budget, TED allocated $380,000 for pavement crackfilling in 2024. Although the award exceeds the amount staff anticipated would be needed for crackfilling, the request is still within budget of the overall project.

 

Account Number

Fund Description

Total Budget Amount

30282200-551502

Capital Projects Fund

$29,448,000

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.