Legislation Details

File #: 26-1237    Version: 1
Type: Procurement Change Order Status: Agenda Ready
File created: 10/19/2026 In control: City Council
On agenda: 11/4/2026 Final action:
Title: Approve the award of Change Order #1 to Contract 26-079, Fire Station 4 Improvements, to Kandu Construction, Inc. for an amount not to exceed $120,145 and a total award of $3,018,145, and for an additional 61 days
Related files: 26-0483B
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #1 to Contract 26-079, Fire Station 4 Improvements, to Kandu Construction, Inc. for an amount not to exceed $120,145 and a total award of $3,018,145, and for an additional 61 days

body

 

DEPARTMENT:                     Department of Public Works

 

SUBMITTED BY:                     Dan Randolph, P.E., Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The City Council awarded Contract 26-079, Fire Station 4 Improvements, to Kandu Construction, Inc. on June 2, 2026, with a closeout date of March 31, 2027.  The purpose of this contract is to renovate the restroom and shower facilities at Fire Station #4 to better accommodate operational needs, support gender equity, and address recommendations from the Center for Public Safety Excellence (CPSE) Accreditation Team. Work also includes construction of the academy training center.

 

DISCUSSION:

This Change Order is requested to address unforeseen soil conditions discovered during construction of the training center. The additional work includes foundation footing excavation and backfill, including mobilization and demobilization as needed, along with any additional work recommended by the geotechnical engineer. The total amount requested is $120,145 with an updated closeout date of May 31, 2027.

 

Contract Award

Original Contract Value

$ 2,898,000

Prior Cumulative Approved Change Orders 

$ 0

Subtotal

$ 2,898,000

(+/-) This Change Order

$ 120,145

Total Contract Value

$ 3,018,145

 

 

FISCAL IMPACT:

CIP#: MB228

 

Fire Station #4 Improvements are charged to the Building Improvements account listed below. The 2026 Budget includes $2,736,037 for the completion of the project. The requested change order of award of $120,145, and total award of $3,018,145, is higher than the budget for this expense. It is anticipated that this overage can be accommodated in the 2026 Budget.

 

Account Number

Fund Description 

Total Budget Amount

 22252200-551500

 Capital Projects

 $2,736,037