CITY COUNCIL AGENDA ITEM
ACTION REQUESTED:
title
Approve the award of Work Order 22-067-WATER-26-02, Construction Engineering Services - Maplebrook Phase II Water Main Improvements, to Crawford, Murphy & Tilly, Inc., for an amount not to exceed $181,800 and for a 16-month term
body
DEPARTMENT: Water Utilities
SUBMITTED BY: Darrell Blenniss, Director
BACKGROUND:
In 2022, the Water Utilities completed a Request for Qualifications (RFQ 22-067) for water main and sanitary sewer projects, and five consultants were shortlisted. The RFQ also stated that the City retains the right to use the services of a successful firm for future phases of a specific project. The short-listed consultants are:
1. Baxter and Woodman
2. Ciorba Group
3. Civil and Environmental Consultants
4. Crawford, Murphy & Tilly
5. Fehr Graham
In January 2026, the Water Utilities issued Work Order 22-067-WATER-26-02 seeking to retain the services of a qualified and experienced consultant to provide construction engineering services for the Maplebrook Phase II Water Main Improvements. Work Order 22-067-WATER-26-02 was issued to consultants on the Water Utilities engineering services shortlist.
The purpose of the project is to replace the aging and deficient water main on the following streets in the Maplebrook Subdivision: Olympus Drive, Cardinal Lane, Dove Court, Tamarack Avenue, Sandpiper Lane and Triton Lane.
DISCUSSION:
|
Work Order Date: |
01/06/2026 |
Notices Sent: |
5 |
|
Opening Date: |
01/27/2026 |
Planholders: |
5 |
|
|
|
Quotations Received: |
2 |
Responses were received from the following vendors:
|
Vendor |
Quotation |
|
Crawford, Murphy & Tilly |
$181,800 |
|
Fehr Graham |
$200,000 |
Crawford, Murphy & Tilly is recommended for selection based on cost and having been prequalified for this type of work as part of the original shortlist selection.
The term of the contract is approximately 16 months from the date of award through June 30, 2027.
FISCAL IMPACT:
CIP #: WU409 - Maplebrook Phase II Water Main Improvements
Construction engineering services for Maplebrook Phase II Water Main Improvements will be charged to the Architect and Engineering Service account listed below. The 2026 Budget includes $219,240 in this account for the completion of this project. The recommended award is favorable to the 2026 Budget.
|
Account Number |
Fund Description |
Total Budget Amount |
|
41251500-531301 |
Water Utilities Fund |
$5,204,829 |