File #: 26-0187    Version: 1
Type: Procurement Change Order Status: Passed
File created: 2/6/2026 In control: City Council
On agenda: 2/17/2026 Final action: 2/17/2026
Title: Approve the award of Change Order #1 to contract 25-289, 2025 New Sidewalk Program, to Triggi Construction, Inc. for an amount not to exceed $24,738.93 and a total award of $334,081.93

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #1 to contract 25-289, 2025 New Sidewalk Program, to Triggi Construction, Inc. for an amount not to exceed $24,738.93 and a total award of $334,081.93

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     Jennifer Louden, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The City Council awarded Contract 25-289 to Triggi Construction, Inc. on October 21, 2025, with a completion date of May 30, 2026. The purpose of this contract is to improve walkability throughout the City per the Comprehensive Sidewalk Policy.

 

This contract is the last of the three-year program approved by the City Council in July 2023.

 

DISCUSSION:

The steep parkway grades in this neighborhood created difficult field conditions that necessitated extra work, including additional pavement removal, HMA asphalt pavement placement, and sod restoration. Staff also worked with several adjacent residents to adjust the sidewalk locations to address concerns related to their driveways and existing trees. Lastly, 4" PVC drainpipes were encountered within the proposed sidewalk alignment, which needed to be rerouted in the field.

 

This contract was approved with a 5% contingency of $15,467.15. To date, no contingency has been utilized. This Change Order is being requested to authorize additional funds in the amount of $9,271.78 beyond the existing contingency. Staff requests use of available contingency funds along with an additional $9,271.78 for a total Change Order amount of $24,738.93.

 

Contract Award

Original Contract

$309,343.00

Prior Cumulative Changes

$0.00

Subtotal

 

$309,343.00

(+) This Change

$24,738.93

Total Contract

 

$334,081.93

 

 

FISCAL IMPACT:

CIP # CS006

 

The Sidewalk Improvement Program is expensed to the Infrastructure account listed below. In 2026, TED included $325,000 in the budget for CS006, the New Sidewalk Improvement Program. It is anticipated that the requested Change Order can be accommodated within the budget.

 

Account Number

Fund Description

Total Budget Amount

30282200-551502

Capital Projects Fund

$24,899,000