File #: 25-0019    Version: 1
Type: Procurement Change Order Status: Agenda Ready
File created: 1/6/2025 In control: City Council
On agenda: 1/21/2025 Final action:
Title: Approve the award of Change Order #1 to Contract 23-294, River Road Water Main Improvements, to Performance Construction and Engineering for an amount not to exceed $198,802.40, for a total award of $5,371,950.47, and for an additional 182 days
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Change Order #1 to Contract 23-294, River Road Water Main Improvements, to Performance Construction and Engineering for an amount not to exceed $198,802.40, for a total award of $5,371,950.47, and for an additional 182 days

body

 

DEPARTMENT:                      Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

On April 2, 2024, the City Council awarded Bid 23-294 to Performance Construction and Engineering for an amount not to exceed $5,173,148.07 to install a water main on River Road from Aurora Avenue to the BNSF right-of-way and on Aurora Avenue from River Road to Wild Cherry Road. 

 

The contract included a completion date of October 31, 2024.

 

DISCUSSION:

Unforeseen site conditions beyond the contractor’s control necessitated this Change Order which includes final balancing changes reflecting as-built quantities for the contract pay items along with extra work items deemed necessary to ensure a successful project.  The major extra work items include an additional 800 feet of water main not quantified in the contract, exploratory work and revisions at various locations, additional valving, additional pavement removal, and remedial work to correct a plan discrepancy at All Saints School.

 

The original contract included a contingency of 3%, or $155,194.44. Staff is requesting additional funds for this Change Order. The contingency will be retained to address any final work items to be completed in the spring. The tables below provide a summary of the award and contingency amount.  

 

Contingency  

Authorized Contingency 

Dollars 

Original Amount 

$  155,194.44

(-) Previously Authorized 

$  0.00

Subtotal 

$  155,194.44

(-) This Change 

$  0.00

Balance Left 

$  155,194.44

 

Contract Award

Original Contract Value

$ 5,173,148.07

Prior Cumulative Approved Change Orders 

$ 0.00

Subtotal

$ 5,173,148.07

(+/-) This Change Order

$ 198,802.40

Total Contract Value

$ 5,371,950.47

 

Additionally, due to the extra work items added to the contract, an extended completion date was required.  To complete this addtional work, staff requests a revised completion date of May 1, 2025.

 

FISCAL IMPACT:

CIP #: WU402 - River Road Water Main and Duct Bank Improvements

 

The requested change order will be covered by underspending from other watermain improvement projects, such as the Royal Oaks Watermain project. Staff will continue to monitor expenses to ensure they remain within the approved budget.

 

Account Number

Fund Description

Total Budget

41251500-551502

Water Utilities Fund

$68,654,488