CITY COUNCIL AGENDA ITEM
ACTION REQUESTED:
title
Approve the award of Bid 22-030, 2022 Northeast Waterworks Phase 1 Improvements, to Dahme Mechanical Industries for an amount not to exceed $999,888.77 and a 3% contingency
body
DEPARTMENT: Water Utilities
SUBMITTED BY: Darrell Blenniss, Director
BOARD/COMMISSION REVIEW:
N/A
BACKGROUND:
The Northeast Waterworks standpipe was originally constructed in 1966. The pump station and generator room were constructed in 1982. The PAS 15 water connection, chlorine system and SCADA were constructed in 1991. Because the different systems in this station were built over various decades, system integration has always been an issue. In addition, many of the station assets, such as the generator, are in poor condition and experience decreased reliability. Also, the station’s chlorine system requires replacement and installation of a chlorine scrubber to meet current regulations.
In December 2021, the Water Utilities issued Bid 22-030, Northeast Waterworks Phase 1 Improvements. The project includes replacement of the existing standby generator, automatic transfer switch and associated electrical and SCADA work. It also includes replacing the existing chlorination equipment and control system, improvements to the chlorine room, chlorine scrubber and installation of one additional chlorine booster pump and associated piping.
DISCUSSION:
Advertisement Date: 12/30/2021 Notices Sent: 244
Bid Opening Date: 1/28/2022 Plan holders: 24
Proposals Received: 3
Vendors Name |
Proposed Cost |
Dahme Mechanical Industries |
$999,888.77 |
Engineers Estimate |
$1,328,250.00 |
Integral Construction |
$1,103,200.00 |
Following the bid opening, Volt Electric Inc. was determined to be non-responsive due to a mathematical error.
The completion date of this project is December 15, 2022.
FISCAL IMPACT:
CIP: WU007
Water Supply projects are expensed to the infrastructure account listed below, as part of the capital improvement program. A total of $3,090,000 is budgeted in WU007 in 2022. The requested award is within budget.
Account Number |
Fund Description |
Total Budget Amount |
41252000-551502 |
Water Capital Fund |
$27,438,275 |
Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.