File #: 25-1651    Version: 1
Type: Procurement Award Status: Agenda Ready
File created: 12/9/2025 In control: City Council
On agenda: 1/20/2026 Final action:
Title: Approve the award of Bid 25-298, Southwest Waterworks Generator Replacement, to Pro Temp of Illinois, Inc. for an amount not to exceed $320,500 plus a 5% contingency
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 25-298, Southwest Waterworks Generator Replacement, to Pro Temp of Illinois, Inc. for an amount not to exceed $320,500 plus a 5% contingency

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The existing generator at Southwest Water Works (SWWW) was manufactured in 1994 and has been serving that facility since 2013.

 

With the improvements at SWWW, the generator no longer has the capacity to serve all equipment during a power outage. In addition, the existing generator has reached the end of its service life and requires significant maintenance.

 

On October 24, 2025, the Water Utilities Department issued Bid 25-298 for the Southwest Waterworks Generator Replacement Project. The project includes replacement of the existing generator, the automatic transfer switch (ATS), associated electrical conduits and wiring, and supervisory control and data acquisition (SCADA) system improvements. Additional scope includes installing a generator concrete pad and surrounding sidewalks.

 

DISCUSSION:

 

Advertisement Date:

10/24/2025

Notices Sent:

163

Opening Date:

11/24/2025

Planholders:

23

 

 

Proposals Received:

2

 

Bids were received from the following vendors:

 

Vendors Name

Proposed Cost

Pro Temp of Illinois, Inc.

$320,500

Engineer’s Estimate

$450,000

Connelly Electric Co.

$469,000

 

Staff has performed reference checks, held a pre-award meeting with Pro Temp of Illinois, Inc. and received positive feedback from project references. Staff recommends Pro Temp of Illinois, Inc. for the award as the responsive and responsible bidder for the procurement of construction services, as defined by Section 1-9B-7 of the Procurement Code (RBO-qualified).

 

The term of the contract is from the date of award through the anticipated completion date of March 15, 2027.

 

FISCAL IMPACT:

CIP #: WU071 - Water Facility Generator Replacement - Southwest Water Works

 

The requested award will be charged to the Infrastructure account listed below. The 2026 Budget includes $450,000 for the completion of the project. The requested award, including contingency funds, is within budget.

 

Account Number

Fund Description

Total Budget Amount

41251500-551502

Water Utilities Fund

$86,910,285

 

*Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.