Title: Approve the award of Bid 21-105, 2021 Naperville Heights Water Main Replacement, to Copenhaver Construction, Inc. for an amount not to exceed $3,074,328.50 plus a 3% contingency
Attachments: 1. WU004

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 21-105, 2021 Naperville Heights Water Main Replacement, to Copenhaver Construction, Inc. for an amount not to exceed $3,074,328.50 plus a 3% contingency

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

In April 2021, the Water Utilities issued Bid 21-105, 2021 Naperville Heights Water Main Replacement. The project includes Webster Street, Main Street and 14th Avenue with north and south limits at Bauer Road and Ogden Avenue.

 

The purpose of the project is to replace aging and functionally deficient water main within the Naperville Heights neighborhood. The bulk of the existing water main is four-inch diameter and was built in the 1930s and 1940s. The water main will be replaced with eight-inch diameter water main which will increase fire flows in the area and provide a consistent level of service for residents of the neighborhood.

 

DISCUSSION:

 

Advertisement Date: 4/13/2021                                          Notices Sent: 180

            Bid Opening: 4/30/2021                                          Planholders:    11

                                                                                                                              Proposals Received:   2

 

Vender Name

Proposed Cost

Copenhaver Construction, Inc.

$3,074,328.50

Engineers Estimate

$3,390,000.00

H. Linden & Sons Sewer and Water Inc.

$4,022,740.00

 

Prior to the bid opening Baish Excavating, Clark Dietz Inc. and JJ Henderson and Son, Inc., provided written notice they would not submit bids. Baish stated that the scope of the project was too large for their crews. Clark Dietz could provide engineering, but not crews, and JJ Henderson and Son are not performing this type of work.

The low bid for the project is 9.3% lower than the engineer’s estimate. Given the large discrepancy between the low bid and second bid, Copenhaver reached out to discuss whether something was overlooked within their bid. Upon review of the engineer’s estimate and discussion between staff and Copenhaver, the bidder confirmed the accuracy of their bid.

Staff believes the low bid submitted is reasonable for performing the work as specified. Water Utilities has previous experience with Copenhaver Construction for similar projects and the work was satisfactory.

 

The completion date of this project is October 15, 2021.

 

FISCAL IMPACT:

CIP: WU004

 

Rehabilitation and replacement projects on the water distribution system are expensed to the infrastructure account listed below as part of the capital improvement program. A total of $3,850,000 is budgeted for WU004 in 2021. The requested award is within budget.

 

Account Number

Fund Description

Total Budget Amount

41251500-551502

Water and Wastewater

$26,743,950

 

Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.