File #: 22-0340    Version: 1
Type: Procurement Award Status: Passed
File created: 3/6/2022 In control: City Council
On agenda: 4/5/2022 Final action: 4/5/2022
Title: Approve the award of Bid 22-021, Park Addition Water Main Replacement, to Copenhaver Construction Inc. for an amount not to exceed $4,515,317 plus a 3% contingency
Attachments: 1. WU004, 2. SW035
Related files: 22-1098

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 22-021, Park Addition Water Main Replacement, to Copenhaver Construction Inc. for an amount not to exceed $4,515,317 plus a 3% contingency

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

In February 2022, Water Utilities issued Bid 22-021, Park Addition Water Main Replacement. The project includes Center Street, Ellsworth Street, Brainard Street and Loomis Street from 5th Avenue to Ogden Avenue. The project also includes the replacement of the storm sewer on Ellsworth Street from 5th Avenue to 7th Avenue.

 

The purpose of the project is to replace aging and functionally deficient water mains in the Park Addition subdivision. Water mains vary in size from four inches to 10-inches. The bulk of the existing water main is cast iron installed in the 1930s, with segments of poor-quality ductile iron pipe installed in the 1960s and 1970s. Four and six-inch pipes will be upsized to eight-inch pipes and 10-inch pipes will be upsized to 12-inch pipes in accordance with City standards.

 

The storm sewer on Ellsworth Street is being upsized to a 30-inch pipe to improve stormwater conveyance and drainage characteristics of the area.

 

DISCUSSION:

Advertisement Date:                     2/24/2022                                          Notices Sent:                                                               297

Bid Opening Date:                                          3/16/2022                                          Planholders:                                                               30

                                                                                                                                                   Proposals Received:                     2

 

Bids were received from the following vendors:

 

Firm Name

Total Costs

Copenhaver Construction Inc.

$4,515,317

Engineers Estimate

$4,189,730

Swallow Construction Corporation

$5,211,392

 

The low bid for the project is 7.8% greater than the engineer’s estimate. The discrepancy can be attributed to the following factors:

 

                     material shortages

                     labor shortages

                     generally high rate of inflation

                     international political and economic uncertainty

 

While costs are greater than anticipated, it is not in the best interest of Water Utilities to cancel, delay or re-bid the project. The current economic climate is anticipated to continue for the foreseeable future. Staff worked to negotiate with Copenhaver Construction on a reduction of their submitted bid, however, due to the rapidly rising costs of materials and unprecedented volatility in the industry, Copenhaver was unable to offer a reduction.

 

Staff believes the low bid submitted is reasonable for performing the work as specified. Staff has experience with Copenhaver Construction and finds them to be a capable contractor.

 

The completion date of this project is September 30, 2022.

 

FISCAL IMPACT:

CIP:                     WU004, SW035

                     

The 2022 program for Water Distribution System - Rehabilitation and Replacements (WU004) is budgeted at $7,941,000. The Park Addition water main is one component of that program and is budgeted at $3,918,745. The storm sewer component of the Park Addition project is included in Stormwater Improvements - 8th, Ellsworth and Main (SW035) and is budgeted at $220,000. While the total bid comes in $325,587 more than budgeted, both components are a high priority in the 2022 CIP. Staff will monitor future project bids and adjust the 2022 CIP as needed.

 

Account Number

Fund Description

Total Budget Amount

41252000-551502

Water Capital

$27,438,275

30282200-531301

Capital Projects

$1,836,000

30282200-551502

Capital Projects

$18,083,000

 

Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.