File #: 25-0455    Version: 1
Type: Procurement Award Status: Passed
File created: 4/1/2025 In control: City Council
On agenda: 4/15/2025 Final action: 4/15/2025
Title: Approve the award of Bid 25-032, Storm Sewer Rehabilitation, to Performance Pipelining, Inc. for an amount not to exceed $750,000 plus a 3% contingency

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Bid 25-032, Storm Sewer Rehabilitation, to Performance Pipelining, Inc. for an amount not to exceed $750,000 plus a 3% contingency

body

 

DEPARTMENT:                     Department of Public Works

 

SUBMITTED BY:                     Richard Dublinski, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The Department of Public Works (DPW) maintains the City’s system of storm sewers.  Storm sewers have a functional lifespan of approximately 75 years.  As storm sewer ages, the pipes develop cracks caused by material degradation, soil settlement, root intrusion, and/or adjacent construction.  When a segment of storm sewer approaches the end of its useful life, the extent and severity of pipe degradation results in a high probability for pipe/system failure.  Pipe failure may cause sinkholes in roadway surfaces and may also result in flooding of homes, businesses and/or public rights-of-way.  The City has relined approximately 265,000 linear feet of pipe since the inception of the Storm Sewer Lining Program (SW017) in 2004, which has led to a reduction in localized flooding and related complaints.

 

DPW and the Water Utilities both have sewer lining programs.  The programs are bid separately because the location and size of the pipe is different enough to affect pricing.  The majority of DPW’s storm water system is in the right-of-way, while the Water Utilities has substantially more pipe being lined in residents’ yards, making it more difficult to perform the work.

 

In February 2025, the DPW issued Bid 25-032, Storm Sewer Rehabilitation (8”- 30” Diameter) Cured-In-Place Pipelining, for the rehabilitation of approximately 9,500 feet of storm sewer by the installation of cured-in-place pipe (CIPP).   The contract includes a pre-inspection and cleaning of all pipes, the installation of CIPP, and the inspection of each installation by closed circuit television.

 

DISCUSSION:

 

Advertisement Date:

02/28/225

Notices Sent:

241

Opening Date:

03/25/25

Planholders:

19

 

 

Proposals Received:

6

 

Bids were received from the following vendors:

 

Vendor Name

Proposed Cost

Performance Pipelining, Inc.

$783,324.78

Hoerr Construction

$827,657.00

Visu-Sewer Clean & Seal, Inc.

$864,146.00

Inliner Solutions, LLC

$970,239.00

Insituform Technologies USA, Inc.

$1,070,475.26

National Power Rodding Corporation

$1,986,745.00

 

The scope of work under this contract includes the rehabilitation of approximately 9,500 feet of storm sewer ranging from eight inches to 30 inches in diameter by installation of CIPP as well as the cleaning and televising of the storm sewer.  In 2025, work will be completed in The Fields Unit 2, The Fields, Townhomes of The Fields, Villas of The Fields, Westwind Unit 2, Westwind Unit 4, and Woodlawn subdivisions as well as single-run section repairs in other areas. 

 

The approved 2025 budget for the storm sewer lining program is $650,000. In addition, funding is available through the stormwater management CIP program and the Corrugated Metal Pipe Repair CIP for additional lining projects. The quantities provided within the bid documents are approximate and the City reserves the right to decrease or increase the actual purchased quantity. To stay within budget for this program, DPW reduced the number of locations to be completed.

 

Staff recommends Performance Pipelining, Inc. for the award as the lowest responsive and responsible bidder for the procurement of construction services, as defined by section 1-9B-7 of the Procurement Code (RBO-qualified).

 

The term of this contract is for seven months from date of award to October 15, 2025 with two, one-year options to extend. 

 

FISCAL IMPACT:

CIP #: SW001, SW017 and SW037

 

Storm Sewer Rehabilitation CIPP is expensed to the Infrastructure account listed below.  This work is related to SW017, Storm Sewer Lining Program, for which $650,000 has been budgeted in 2025.  This work is also related to SW001, Annual Stormwater Management Projects, and SW037, Corrugated Metal Pipe Repair, for which $220,000 and $170,000 have been budgeted in 2025.  The requested award is within the budgeted amount for this expense.

 

Account Number

Fund Description

Total Budget Amount

31252200-551502

Capital Projects Fund

$1,950,000