Skip to main content
File #: 26-0222    Version: 1
Type: Procurement Award Status: Passed
File created: 2/11/2026 In control: City Council
On agenda: 3/3/2026 Final action: 3/3/2026
Title: Approve the award of Option Year #2 to Contract 23-242, Electrical Installation, Maintenance, Modifications and Repairs, to Volt Electric, Inc. for an amount not to exceed $137,963 and for a one-year term

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of Option Year #2 to Contract 23-242, Electrical Installation, Maintenance, Modifications and Repairs, to Volt Electric, Inc. for an amount not to exceed $137,963 and for a one-year term

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     Darrell Blenniss, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The City Council awarded contract 23-242 to Volt Electric, Inc. on December 19, 2023, for a one-year term from the date of award until December 31, 2024, with three one-year options to extend. City Council approved Option Year #1 on May 20, 2025, for a seven-month term from the date of award until December 31, 2025.

 

The Water Utilities requires the service of a licensed and bonded electrical contractor to provide on-call labor, materials, equipment and expertise in the installation, maintenance, troubleshooting and repairs of electrical components located at all water supply locations, wastewater pump stations and the Springbrook Water Reclamation Center.

 

DISCUSSION:

During both the original contract terms and the first option year of the contract, Volt Electric, Inc. has performed various electrical repairs at several water sites, including thermal imaging of all Motor Control Centers.

 

Volt Electric, Inc. is requesting a 2.3% increase due to increasing labor costs, which staff finds reasonable. Based on the vendor’s performance, staff recommends extending the contract for the second option year.

 

The term for the second option year is from January 1, 2026, to December 31, 2026, with one option year remaining. 

 

FISCAL IMPACT:

CIP# WU038; WW034

 

Electrical installation, maintenance and repairs are expensed to the Building and Grounds Maintenance, Operational Service, Equipment Maintenance, and Infrastructure accounts listed below in the Water Utility Fund.  A total of $145,000 is budgeted for general maintenance and operating costs. Capital costs will be expensed to the respective CIP as needed. The requested award of $137,963 is within budget.

 

 

Account Number

Fund Description

Total Budget Amount

41251510-531302

Water Utility Fund

$170,000

41251520-531308

Water Utility Fund

$2,040,000

41251530-531303

Water Utility Fund

$157,000

41251500-551502

Water Utility Fund

$86,910,285