File #: 17-239    Version: 1
Type: BID, RFP, RFQ, COOP, SOLE SOURCE, OPTION YEAR Status: Passed
File created: 4/5/2017 In control: City Council
On agenda: 4/18/2017 Final action: 4/18/2017
Title: Approve the Award of Bid 17-043, Bar Screen Replacement Project, to Joseph J. Henderson & Son, Inc. for an amount not to exceed $1,205,000, plus a 3% contingency.
Attachments: 1. CIP Page - WWU39.pdf

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the Award of Bid 17-043, Bar Screen Replacement Project, to Joseph J. Henderson & Son, Inc. for an amount not to exceed $1,205,000, plus a 3% contingency.

body

 

DEPARTMENT:                     Water Utilities

 

SUBMITTED BY:                     James Holzapfel, Water Utilities Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The Water Utilities issued Bid 17-043 seeking contractors to complete the demolition and installation of new bar screens, washer and press equipment, slide gates, process piping, plumbing, ventilation, electrical and instrumentation and control at the Springbrook Water Reclamation Center.

 

The existing screening equipment was originally installed in 1981 and operates 365 days a year. The equipment is at the end of useful economic life. Additionally, the current bar screens are not satisfactory for future process changes needed to implement phosphorous removal. The proposed project will replace the existing screening equipment with finer screens and a fully automated system required for plant operations. Finer screening will reduce the amount of debris that enters and disrupts the treatment process.

 

DISCUSSION:

 

Advertisement Date:

03/03/2017

Notices Sent:

 187

Opening Date:

03/30/2017

Planholders:

   20

 

 

Bids Received:

     3  

 

BID TABULATION

The following bids were received:

 

Company Name

Bid Amount

Joseph J. Henderson & Son, Inc.

$1,205,000

Manusos General Contracting, Inc.

$1,323,000

Allan Mack & Sons, Inc.

$1,404,000

Engineer’s Estimate

$1,675,000

 

The Engineer’s Estimate was based on budgetary numbers received from vendors. During the bidding process, equipment vendors may have adjusted pricing due to competition from three manufacturers. 

 

Joseph J. Henderson & Son, Inc., has successfully completed past projects for the Water Utilities at the Springbrook Water Reclamation Center.

 

All work under this contract has a completion date of April 1, 2018.

 

 

FISCAL IMPACT:

CIP #: WWU39

 

WWU39 - SWRC Influent Headworks Upgrades & Improvements

WWU39 includes removal and replacement of existing screens and screening washers at the influent headworks of the Springbrook Water Reclamation Plant. Bar screens and screening washers/compacters remove trash, and other debris from entering the downstream water treatment process.

 

Upgrades and improvements to the Springbrook Water Reclamation Plant are expensed to the Capital Improvement account listed below. A total of $1,500,000 is budgeted for WWU39 in CY2017. The requested award is within budget.

 

 

Account Number

Fund Description

Total Budget Amount

430-3490-537-70-89

Water & Wastewater

$8,852,500

 

Per Council directive, contingency on construction projects is set at 3% on projects over $500,000 and 5% on projects under $500,000.