Legislation Details

File #: 26-1051    Version: 1
Type: Procurement Award Status: Agenda Ready
File created: 8/31/2026 In control: City Council
On agenda: 9/15/2026 Final action:
Title: Approve the award of RFQ 26-075, Phase III - 87th Street Bridge Over Springbrook Creek, to Civiltech Engineering, Inc. for an amount not to exceed $549,653
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

CITY COUNCIL AGENDA ITEM

 

ACTION REQUESTED:
title

Approve the award of RFQ 26-075, Phase III - 87th Street Bridge Over Springbrook Creek, to Civiltech Engineering, Inc. for an amount not to exceed $549,653

body

 

DEPARTMENT:                     Transportation, Engineering and Development

 

SUBMITTED BY:                     Jennifer Louden, Director

 

BOARD/COMMISSION REVIEW:
N/A

 

BACKGROUND:

The 87th Street Bridge sits on the county boundary line between DuPage County and Will County. The bridge is located on 87th Street between Plainfield-Naperville Road and Modaff Road and crosses over Springbrook Creek. The original structure was constructed in 1961. A feasibility study was completed in 2018 that recommended that the existing bridge be replaced. Preliminary engineering began in 2020, and the Illinois Department of Transportation (IDOT) issued design approval in 2023. Design engineering will be complete in 2026.

 

Because federal funding will be used for the 87th Street Bridge reconstruction project, a Quality-Based Selection (QBS) process is required for the consultant selection.

 

DISCUSSION:

On March 2026, the Transportation, Engineering and Development Business Group (TED) issued RFQ 26-075, Phase III - 87th Street Bridge Over Springbrook Creek to solicit responses from experienced and qualified vendors to perform construction engineering services. The selected vendor will provide the resident engineer, inspectors, and other technical personnel necessary to observe, monitor, and document the contractor’s progress on the project from the start of field operations to final completion.

 

Responses were received from the following vendors:

 

Alfred Benesch & Company

EXP U.S. Services Inc.

Bowman Consulting Group Ltd.

Pinpoint Precision Engineering

Civiltech Engineering, Inc.

Thomas Engineering Group, LLC

 

A selection committee comprised of staff from TED evaluated the responses, which were scored based upon the criteria set forth in the RFQ:

 

1. Project Approach - (20%)

2. Qualifications of Proposed Personnel - (30%)

3. Project Experience - (45%)

4. Completeness of the Proposal - (5%)

 

After review and scoring of the responses, the vendor with the highest qualification score, Civiltech Engineering, Inc., is recommended for award.  The table below provides a summary of the final qualification scores:

 

Vendor

Qualification Score

 Alfred Benesch & Company

88

 Bowman Consulting Group Ltd.

76.5

 Civiltech Engineering, Inc.

98

 EXP U.S. Services Inc.

73.25

Pinpoint Precision Engineering

48

Thomas Engineering Group, LLC

81.25

 

The term of the contract is two years from execution of the Consultant Services Agreement, with two one-year options to extend.

 

FISCAL IMPACT:

CIP#: BR019 - 87th Street Bridge over Springbrook Creek

 

Phase III engineering services for the 87th Street Bridge over Springbrook Creek are expensed to the Architect and Engineer Services account listed below. These services are required to complete BR019, the 87th Street Bridge over Springbrook Creek reconstruction. TED included $145,000 in the 2026 budget for expenses related to BR019, which is sufficient to accommodate the anticipated 2026 expenses associated with this award. Staff will ensure sufficient funds are included in future budgets to support out years associated with this award.

 

Account Number

Fund Description

Total Budget Amount

30282200-531301

Capital Projects Fund

$3,028,000