CITY COUNCIL AGENDA ITEM
ACTION REQUESTED:
title
Approve the award of Option Year One to Contract 22-058, Storm Sewer Lining, to Hoerr Construction for an amount not to exceed $650,000, and a 3% contingency
body
DEPARTMENT: Department of Public Works
SUBMITTED BY: Richard Dublinski, Director
BOARD/COMMISSION REVIEW:
N/A
BACKGROUND:
The Department of Public Works (DPW) maintains the City’s system of storm sewers. Storm sewers have a functional lifespan of approximately 75 years. As a storm sewer ages, the pipes develop cracks caused by material degradation, soil settlement, root intrusion, and/or adjacent construction. When a segment of storm sewer approaches the end of its useful life, the extent and severity of pipe degradation results in a high probability for pipe/system failure. Pipe failure may cause sinkholes in roadway surfaces and may also result in flooding of homes, businesses and/or public rights-of-way. The City has relined approximately 240,000 linear feet of pipe since the inception of the Storm Sewer Lining Program (SW017) in 2004, which has led to a reduction in localized flooding and related complaints.
In February 2022, the City Council awarded Bid 22-058, Storm Sewer Lining, to Hoerr Construction for the rehabilitation of storm sewer by the installation of cured-in-place pipe (CIPP). The contract includes a pre-inspection and cleaning of all pipes, the installation of CIPP, and the inspection of each completed installation by closed circuit television. The term of this contract was for seven months from date of award to October 15, 2022 with two, one-year options to extend.
DISCUSSION:
During the initial year of the contract, Hoerr Construction completed the rehabilitation of approximately 11,100 feet of storm sewer ranging from 8 inches to 30 inches in diameter by installation of CIPP as well as the cleaning and televising of the storm sewer. In 2022, work was completed in Lakewood Crossing and Ivy Ridge subdivisions as well as single run section repairs in other areas.
Based upon the vendor’s performance, DPW would like to extend the contract for the first option year. For 2023, work will continue in the Lakewood Crossing and Ivy Ridge subdivisions as well as in the Feldott and Wildflower subdivisions.
The term of the first option year is April 1, 2023 through March 31, 2024, with one additional option year to extend.
FISCAL IMPACT:
CIP #: SW017
Storm Sewer Rehabilitation CIP is expensed to the Infrastructure account listed below. This work is related to SW017, Storm Sewer Lining Program, for which $650,000 has been budgeted in 2023. The requested award is within the budgeted amount for this expense.
Account Number |
Fund Description |
Total Budget Amount |
31252200-551502 |
Capital Projects Fund |
$3,575,000 |